13627 W CHANDLER BLVD 91401

Certificate Information: 13627 W CHANDLER BLVD 91401

Application / Permit
21014-20000-05093
Plan Check / Job No.
B21VN13758
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL;REMOVE DWELLING EXCEPT FOR 10 LINEAR FEET OF WALL ON SOUTH SIDE OF LOT; ADD 48' X 55'-6" SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA -13D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/8/2022
Issuing Office
Current Status
CofO Issued on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 SELLA BENYAMIN
Corrections Issued 10/26/2021 SELLA BENYAMIN
Quality Review Completed 10/28/2021 STEVEN KIM
Building Plans Picked Up 11/1/2021 APPLICANT
Plan Check Approved 2/3/2022 SELLA BENYAMIN
Issued 2/8/2022 APPLICANT
CofO in Progress 8/18/2022 RICHARD DOCKUS
Permit Finaled 8/27/2022 DEROLD HAUFF
CofO Issued 8/27/2022 DEROLD HAUFF
Permit Finaled 8/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 11/30/2021 CARLOS AGUILERA
Trees in Parkway Cleared 11/30/2021 ADALBERTO VERA
Eng Process Fee Ord 176,300 Cleared 12/6/2021 CARLOS AGUILERA
Sewer availability Cleared 12/6/2021 CARLOS AGUILERA
Low Impact Development Cleared 1/5/2022 TA ANH
Roof/Waste drainage to street Cleared 1/24/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/28/2022 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/22/2022 Corrections Issued RICHARD DOCKUS
Underground Mechanical 2/22/2022 Partial Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 2/24/2022 Off-Hour Fees Due
Deputy Reinf. Concrete 2/25/2022 No Access for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 2/28/2022 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Partial Inspection KRISTEN CAUSEY
Deputy Wood Construction 3/21/2022 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Not Ready for Inspection RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Approved RICHARD DOCKUS
HVAC-Rough 3/30/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 3/30/2022 Approved JOHN HAYES
Interior/Exterior Lathing 3/31/2022 Partial Approval RICHARD DOCKUS
Shower Pan 3/31/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 4/1/2022 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 4/1/2022 Approved RICHARD DOCKUS
Green Building Rough 4/1/2022 Approved RICHARD DOCKUS
HVAC-Rough 4/1/2022 Corrections Issued RICHARD DOCKUS
HVAC-Rough 4/5/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 4/5/2022 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 4/6/2022 Conditional Approval ALAN MORELOS
Interior/Exterior Lathing 4/6/2022 Partial Approval ALAN MORELOS
Insulation 4/8/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 4/13/2022 Approved RICHARD DOCKUS
Drywall Nailing 4/13/2022 Approved RICHARD DOCKUS
HVAC-Final 6/10/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 6/29/2022 Approved RICHARD DOCKUS
HVAC-Final 6/29/2022 Approved RICHARD DOCKUS
PLUMBING-Final 6/29/2022 Approved RICHARD DOCKUS
Gas Test 7/6/2022 Approved DEANDRE HOFFMAN
Final 8/1/2022 Corrections Issued RICHARD DOCKUS
Green Building Final 8/1/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 8/1/2022 Approved RICHARD DOCKUS
Final 8/17/2022 OK to Issue CofO RICHARD DOCKUS
Footing/Foundation/Slab 8/22/2022 Partial Approval RICHARD DOCKUS
Service/Power Release 8/22/2022 Approved RICHARD DOCKUS