13627 W CHANDLER BLVD 91401
Certificate Information: 13627 W CHANDLER BLVD 91401
- Application / Permit
- 21014-20000-05093
- Plan Check / Job No.
- B21VN13758
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL;REMOVE DWELLING EXCEPT FOR 10 LINEAR FEET OF WALL ON SOUTH SIDE OF LOT; ADD 48' X 55'-6" SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA -13D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 2/8/2022
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | SELLA BENYAMIN |
| Corrections Issued | 10/26/2021 | SELLA BENYAMIN |
| Quality Review Completed | 10/28/2021 | STEVEN KIM |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
| Plan Check Approved | 2/3/2022 | SELLA BENYAMIN |
| Issued | 2/8/2022 | APPLICANT |
| CofO in Progress | 8/18/2022 | RICHARD DOCKUS |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
| CofO Issued | 8/27/2022 | DEROLD HAUFF |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 11/30/2021 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 11/30/2021 | ADALBERTO VERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/6/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 1/5/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/24/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/28/2022 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/22/2022 | Corrections Issued | RICHARD DOCKUS |
| Underground Mechanical | 2/22/2022 | Partial Approval | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 2/24/2022 | Off-Hour Fees Due | |
| Deputy Reinf. Concrete | 2/25/2022 | No Access for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 2/28/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Partial Inspection | KRISTEN CAUSEY |
| Deputy Wood Construction | 3/21/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 3/30/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/30/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/31/2022 | Partial Approval | RICHARD DOCKUS |
| Shower Pan | 3/31/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/1/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 4/1/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 4/1/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 4/1/2022 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Rough | 4/5/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 4/5/2022 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/6/2022 | Conditional Approval | ALAN MORELOS |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | ALAN MORELOS |
| Insulation | 4/8/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/13/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 4/13/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 6/10/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 6/29/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 6/29/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 6/29/2022 | Approved | RICHARD DOCKUS |
| Gas Test | 7/6/2022 | Approved | DEANDRE HOFFMAN |
| Final | 8/1/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 8/1/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 8/1/2022 | Approved | RICHARD DOCKUS |
| Final | 8/17/2022 | OK to Issue CofO | RICHARD DOCKUS |
| Footing/Foundation/Slab | 8/22/2022 | Partial Approval | RICHARD DOCKUS |
| Service/Power Release | 8/22/2022 | Approved | RICHARD DOCKUS |