5628 N FAUST AVE 91367

Certificate Information: 5628 N FAUST AVE 91367

Application / Permit
21014-20000-05090
Plan Check / Job No.
B21VN13748
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 8' X 13'- 8" (110 SQ FT) ADDITION TO EXTEND (E) BEDROOM AND ADD BATHROOM. AND 4'-5" X 6'-1" (27 SQ FT) ADDITION TO BUMP OUT (E) FRONT DOOR. ALL WORK PER ENGINEEERING.
Permit Issued
Issued on 10/26/2021
Issuing Office
Current Status
CofO Issued on 3/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2021 APPLICANT
Assigned to Plan Check Engineer 10/12/2021 OMAR GARNICA
Corrections Issued 10/12/2021 OMAR GARNICA
Plan Check Approved 10/20/2021 OMAR GARNICA
Building Plans Picked Up 10/21/2021 APPLICANT
Issued 10/26/2021 APPLICANT
CofO in Progress 12/9/2021 TROY SANDERS
Permit Finaled 3/6/2023 DANIEL ORRANTE
CofO Issued 3/6/2023 DANIEL ORRANTE
Permit Finaled 3/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/14/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 10/14/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Knudsen Mark Curtis; Lic. No.: 544786-B 22639 MIRANDA ST      WOODLAND HILLS, CA 91367
Engineer Pall,, Avtar S; Lic. No.: S4333 22115 MICHALE ST      WEST HILLS, CA 91304

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/28/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 11/4/2021 Partial Approval TROY SANDERS
Green Building Rough 11/4/2021 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 11/10/2021 Approved TROY SANDERS
ELECTRICAL-Rough 11/10/2021 Approved TROY SANDERS
Green Building Rough 11/10/2021 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 11/10/2021 Approved TROY SANDERS
Shower Pan 11/10/2021 Approved TROY SANDERS
Insulation 11/15/2021 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/15/2021 Approved MORRIS JACKSON
BUILDING-Rough-Frame 11/17/2021 Approved TROY SANDERS
Drywall Nailing 11/17/2021 Approved TROY SANDERS
Green Building Rough 11/17/2021 Approved TROY SANDERS
Interior/Exterior Lathing 11/17/2021 Approved TROY SANDERS
Final 12/8/2021 OK to Issue CofO TROY SANDERS
Green Building Final 12/8/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Approved TROY SANDERS