19548 W MERRIDY ST 91324
Certificate Information: 19548 W MERRIDY ST 91324
- Application / Permit
- 21014-20000-05073
- Plan Check / Job No.
- B21VN13684
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE 3'-4" X 19'-9" PORTION AND ENCLOSE 3'-6" X 19'-9" OF FRONT PORCH AND ADD 13'-5" X 16'-8" FOR (N) ENTRY & FRONT PORCH AND REMODEL (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/24/2021
- Issuing Office
- Current Status
- CofO Issued on 8/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2021 | RAPHAEL ROSAS |
| Corrections Issued | 10/12/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 11/8/2021 | RAPHAEL ROSAS |
| Issued | 11/24/2021 | APPLICANT |
| Building Plans Picked Up | 11/29/2021 | APPLICANT |
| CofO in Progress | 7/30/2022 | JEFFREY PARD |
| Permit Finaled | 8/15/2022 | JOHN JANSON |
| CofO Issued | 8/15/2022 | JOHN JANSON |
| Permit Finaled | 8/15/2022 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/13/2021 | GABRIEL ROBLES |
| Watercourse | Cleared | 10/13/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 11/12/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/3/2021 | Partial Approval | JEFFREY PARD |
| Deputy Drilled-In Anchors | 1/13/2022 | Conditional Approval | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 1/19/2022 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 1/28/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 1/28/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/18/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 3/18/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 3/18/2022 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 3/18/2022 | Approved | JEFFREY PARD |
| Deputy Wood Construction | 3/24/2022 | Conditional Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 3/29/2022 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Approved | DAVID SCANTLIN |
| Insulation | 4/13/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 4/13/2022 | Partial Approval | KRISTEN CAUSEY |
| Drywall Nailing | 4/21/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 7/29/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 7/29/2022 | Approved | JEFFREY PARD |
| Final | 7/29/2022 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 7/29/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 7/29/2022 | Approved | JEFFREY PARD |
| HVAC-Final | 7/29/2022 | Approved | JEFFREY PARD |
| PLUMBING-Final | 7/29/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 7/29/2022 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 7/29/2022 | Approved | JEFFREY PARD |