7509 N BALBOA BLVD 91406
Certificate Information: 7509 N BALBOA BLVD 91406
- Application / Permit
- 21014-20000-05066
- Plan Check / Job No.
- B21VN13642
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD NEW 11'-0" x 6'-0" BATHROOM AND 22'-2" x 16'-2" ATTACHED PATIO COVER TO (E) S.F.D. AND ADD 10'-5" x 4'-4" STORAGE PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 05/21/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Current Status
- CofO in Progress on 8/16/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | ALFRED RAMIREZ |
| Corrections Issued | 10/7/2021 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 5/19/2022 | ALFRED RAMIREZ |
| Issued | 6/3/2022 | APPLICANT |
| Building Plans Picked Up | 6/3/2022 | APPLICANT |
| CofO in Progress | 8/16/2023 | MICKEY YAMASHITA |
| CofO in Progress | 7/1/2024 | MICKEY YAMASHITA |
| CofO in Progress | 7/1/2024 | MICKEY YAMASHITA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/12/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/16/2022 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Rough | 6/16/2022 | Not Ready for Inspection | THOMAS WOODS |
| Pre-Inspection | 6/16/2022 | Approved | THOMAS WOODS |
| Footing/Foundation/Slab | 6/24/2022 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 7/19/2022 | Approved | THOMAS WOODS |
| BUILDING-Rough-Frame | 7/25/2022 | Approved | THOMAS WOODS |
| Drywall Nailing | 7/25/2022 | Approved | THOMAS WOODS |
| ELECTRICAL-Final | 7/25/2022 | Approved | THOMAS WOODS |
| ELECTRICAL-Rough | 7/25/2022 | Approved | THOMAS WOODS |
| Final | 7/25/2022 | Conditional Approval | THOMAS WOODS |
| Green Building Final | 7/25/2022 | Approved | THOMAS WOODS |
| Green Building Rough | 7/25/2022 | Approved | THOMAS WOODS |
| HVAC-Final | 7/25/2022 | Approved | THOMAS WOODS |
| HVAC-Rough | 7/25/2022 | Approved | THOMAS WOODS |
| PLUMBING-Final | 7/25/2022 | Approved | THOMAS WOODS |
| PLUMBING-Rough | 7/25/2022 | Approved | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Approved | THOMAS WOODS |
| Smoke Detectors | 7/25/2022 | Approved | THOMAS WOODS |
| Final | 3/20/2024 | Conditional Approval | MICKEY YAMASHITA |
| Final | 7/1/2024 | OK to Issue CofO | MICKEY YAMASHITA |