11844 W PEORIA ST 91352

Certificate Information: 11844 W PEORIA ST 91352

Application / Permit
21014-20000-05054
Plan Check / Job No.
B21VN13598
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
566 SQ. FT. ADDITION TO AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) and (d).
Permit Issued
Issued on 7/18/2022
Issuing Office
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 SELLA BENYAMIN
Corrections Issued 10/26/2021 SELLA BENYAMIN
Applicant returned to address corrections 6/17/2022 ALEC MOUSAKHANIAN
Plan Check Approved 7/18/2022 ALEC MOUSAKHANIAN
Issued 7/18/2022 APPLICANT
Building Plans Picked Up 7/21/2022 APPLICANT
CofO in Progress 11/6/2025 MATTHEW NELSON
CofO Issued 12/18/2025 RUBEN SALAS
Permit Finaled 12/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/24/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 12/13/2021 JOSE DUARTE-DIAZ
Low Impact Development Cleared 5/26/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/31/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 6/7/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/25/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Underground Mechanical 7/25/2022 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 8/12/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Sewer 8/12/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 8/18/2022 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 8/18/2022 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 8/18/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Sewer 8/18/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 9/2/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 9/2/2022 Partial Approval CHRISTOPHER DELLEFIELD
Wood Frame 9/2/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 9/6/2022 Partial Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 9/6/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/8/2022 Conditional Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 9/8/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 9/8/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 9/8/2022 Conditional Approval CHRISTOPHER DELLEFIELD
MERV13>=Rough 9/8/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 9/8/2022 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 4/18/2023 No Access for Inspection MATTHEW NELSON
Pre-Inspection 4/24/2023 Corrections Issued MATTHEW NELSON
HVAC-Rough 5/15/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/22/2023 Approved MATTHEW NELSON
Insulation 6/23/2023 Approved MATTHEW NELSON
Drywall Nailing 7/21/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/21/2023 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 8/25/2023 Not Ready for Inspection WILLIAM WREN
Interior/Exterior Lathing 9/1/2023 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Partial Inspection MATTHEW NELSON
Final 9/18/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 9/18/2025 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Final 9/18/2025 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 9/18/2025 Approved MISAEL ESPARZA
Final 10/7/2025 Not Ready for Inspection MATTHEW NELSON
Green Building Final 10/7/2025 Approved MATTHEW NELSON
MERV13>=Final 10/7/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/7/2025 SGSOV Approved MATTHEW NELSON
Final 11/5/2025 OK to Issue CofO MATTHEW NELSON