7128-7130 N MAMMOTH AVE 91405
Certificate Information: 7128-7130 N MAMMOTH AVE 91405
- Application / Permit
- 21014-20000-05034
- Plan Check / Job No.
- B21VN13533
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERTING THE EXISTING ATTACHED GARAGE, DEN, AND LAUNDRY TO AN ATTACHED ACCESSORY DWELLING UNIT 790 SF PER STATE LAW
- Permit Issued
- Issued on 4/22/2022
- Issuing Office
- Current Status
- CofO Issued on 7/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2021 | CARLOS MONTES |
| Corrections Issued | 10/11/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 11/18/2021 | CARLOS MONTES |
| Plan Check Approved | 12/23/2021 | CARLOS MONTES |
| Issued | 4/22/2022 | APPLICANT |
| CofO in Progress | 7/21/2023 | ROBERT GOLD |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
| CofO Issued | 7/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/15/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Manuel Francisco Bran Co Inc; Lic. No.: 904448-B | 7065 CANTALOUPE AVE VAN NUYS, CA 91405 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/12/2022 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/8/2022 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/8/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Rough | 9/8/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Rough | 9/8/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 9/8/2022 | Corrections Issued | RICHARD DOCKUS |
| Special/Order Compliance | 9/8/2022 | Approved | ROBERT GOLD |
| Insulation | 1/6/2023 | Not Ready for Inspection | WILLIAM WREN |
| Insulation | 1/10/2023 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Rough | 1/10/2023 | Corrections Issued | JOHN COLEMAN |
| Wood Frame | 1/10/2023 | Corrections Issued | JOHN COLEMAN |
| Pre-Inspection | 3/17/2023 | Partial Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 4/5/2023 | Approved | RYAN SALAZAR |
| Insulation | 4/5/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 4/5/2023 | Conditional Approval | RYAN SALAZAR |
| Wood Frame | 4/5/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/18/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/27/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 6/27/2023 | Approved | RYAN SALAZAR |
| Final | 6/27/2023 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 6/27/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 6/27/2023 | Approved | RYAN SALAZAR |
| HVAC-Final | 6/27/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 6/27/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 6/27/2023 | Approved | RYAN SALAZAR |
| Green Building Final | 7/11/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 7/11/2023 | Approved | RYAN SALAZAR |
| Final | 7/21/2023 | OK to Issue CofO | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 7/21/2023 | SGSOV Approved | ROBERT GOLD |