Permit Issued
Issued on 4/22/2022
Issuing Office
Current Status
CofO Issued on 7/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2021 APPLICANT
Assigned to Plan Check Engineer 10/8/2021 CARLOS MONTES
Corrections Issued 10/11/2021 CARLOS MONTES
Applicant returned to address corrections 11/18/2021 CARLOS MONTES
Plan Check Approved 12/23/2021 CARLOS MONTES
Issued 4/22/2022 APPLICANT
CofO in Progress 7/21/2023 ROBERT GOLD
Permit Finaled 7/21/2023 DANIEL ORRANTE
CofO Issued 7/21/2023 DANIEL ORRANTE
Permit Finaled 7/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/14/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 10/15/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 10/18/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Manuel Francisco Bran Co Inc; Lic. No.: 904448-B 7065 CANTALOUPE AVE      VAN NUYS, CA 91405

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/12/2022 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 9/8/2022 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 9/8/2022 Corrections Issued RICHARD DOCKUS
Green Building Rough 9/8/2022 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 9/8/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 9/8/2022 Corrections Issued RICHARD DOCKUS
Special/Order Compliance 9/8/2022 Approved ROBERT GOLD
Insulation 1/6/2023 Not Ready for Inspection WILLIAM WREN
Insulation 1/10/2023 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 1/10/2023 Corrections Issued JOHN COLEMAN
Wood Frame 1/10/2023 Corrections Issued JOHN COLEMAN
Pre-Inspection 3/17/2023 Partial Inspection JOHN COLEMAN
ELECTRICAL-Rough 4/5/2023 Approved RYAN SALAZAR
Insulation 4/5/2023 Approved RYAN SALAZAR
PLUMBING-Rough 4/5/2023 Conditional Approval RYAN SALAZAR
Wood Frame 4/5/2023 Approved RYAN SALAZAR
Drywall Nailing 4/18/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 6/27/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 6/27/2023 Approved RYAN SALAZAR
Final 6/27/2023 Corrections Issued RYAN SALAZAR
Green Building Final 6/27/2023 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 6/27/2023 Approved RYAN SALAZAR
HVAC-Final 6/27/2023 Approved RYAN SALAZAR
PLUMBING-Final 6/27/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Not Ready RYAN SALAZAR
Smoke Detectors 6/27/2023 Approved RYAN SALAZAR
Green Building Final 7/11/2023 Approved RYAN SALAZAR
PLUMBING-Final 7/11/2023 Approved RYAN SALAZAR
Final 7/21/2023 OK to Issue CofO ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Approved ROBERT GOLD