5626 N CANTALOUPE AVE 91401

Certificate Information: 5626 N CANTALOUPE AVE 91401

Application / Permit
21014-20000-05015
Plan Check / Job No.
B21VN13500
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
210 SQ. FT. ADDITION TO SFD OF A NEW MASTER BEDROOM, INTERIOR REMODEL TO THE (E) KITCHEN, BATHROOM, AND BEDROOM. ALTERATIONS TO CREATE A NEW POWDER ROOM, LAUNDRY, BATHROOM AND WALK IN CLOSET. AND REMOVE AND REPLACE ALL WINDOWS.
Permit Issued
Issued on 10/28/2021
Issuing Office
Current Status
CofO Issued on 5/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 LUISANGEL VALENZUELA
Corrections Issued 10/8/2021 LUISANGEL VALENZUELA
Issued 10/28/2021 APPLICANT
Building Plans Picked Up 10/29/2021 APPLICANT
CofO in Progress 4/20/2022 MICHAEL TEMPLE
Permit Finaled 5/13/2022 MICHAEL SMITH
CofO Issued 5/13/2022 MICHAEL SMITH
Permit Finaled 5/13/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/13/2021 CARLOS AGUILERA
Sewer availability Cleared 10/13/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/14/2021 CARLOS AGUILERA

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/12/2021 Corrections Issued RICHARD DOCKUS
Deputy Drilled-In Anchors 11/15/2021 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 11/17/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 11/23/2021 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 12/3/2021 Not Ready for Inspection DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Partial Inspection DAVID MATSON
Green Building Rough 12/3/2021 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 12/28/2021 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 12/28/2021 Approved RICHARD DOCKUS
Green Building Rough 12/28/2021 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 12/28/2021 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 12/28/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 1/3/2022 Corrections Issued RAUL OLAGI
Green Building Rough 1/3/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 1/3/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 1/11/2022 Corrections Issued DAVID MATSON
Green Building Rough 1/11/2022 Corrections Issued DAVID MATSON
Rough-Elec/Plmb/HVAC 1/11/2022 Corrections Issued DAVID MATSON
BUILDING-Rough-Frame 1/14/2022 Approved RICHARD DOCKUS
Green Building Rough 1/14/2022 Approved RICHARD DOCKUS
Insulation 1/26/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 1/26/2022 Partial Approval ALAN MORELOS
Drywall Nailing 2/2/2022 Approved JENNIFER RABUCHIN
Shower Pan 2/2/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/4/2022 Approved ALAN MORELOS
Final 4/14/2022 Corrections Issued RICHARD DOCKUS
Green Building Final 4/14/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 4/14/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 4/14/2022 Approved RICHARD DOCKUS
Final 4/19/2022 OK to Issue CofO MICHAEL TEMPLE