8133 N GENESTA AVE 91406

Certificate Information: 8133 N GENESTA AVE 91406

Application / Permit
21014-20000-05014
Plan Check / Job No.
B21VN13498
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD NEW 18'-0" x 15'-0" AND INTERIOR REMODEL TO THE (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/22/2021
Issuing Office
Current Status
CofO Issued on 9/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 ALFRED RAMIREZ
Corrections Issued 10/7/2021 ALFRED RAMIREZ
Issued 10/22/2021 APPLICANT
Building Plans Picked Up 10/25/2021 APPLICANT
CofO in Progress 9/9/2022 RAUL OLAGI
CofO Issued 9/12/2022 MICHAEL SMITH
Permit Finaled 9/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/7/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/12/2021 CARLOS AGUILERA

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Green Works Construction & Design Inc; Lic. No.: 936962-B 20301 VENTURA BLVD #222      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/11/2022 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 3/15/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 4/8/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/20/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 4/20/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Partial Approval RAUL OLAGI
Insulation 4/21/2022 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 5/12/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 5/12/2022 Approved RAUL OLAGI
HVAC-Rough 5/12/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/12/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/19/2022 Approved RAUL OLAGI
ELECTRICAL-Rough 5/19/2022 Approved RAUL OLAGI
HVAC-Rough 5/19/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/19/2022 Partial Approval RAUL OLAGI
Green Building Rough 5/27/2022 Approved RAUL OLAGI
Insulation 5/27/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/27/2022 Approved RAUL OLAGI
Shower Pan 5/27/2022 Approved RAUL OLAGI
Drywall Nailing 6/3/2022 Approved JAVIER RAMOS JR
Drywall Nailing 6/6/2022 Approved ALAN MORELOS
Rough-Elec/Plmb/HVAC 8/17/2022 Partial Inspection RAUL OLAGI
Special/Order Compliance 8/17/2022 Corrections Issued RAUL OLAGI
Final 8/26/2022 Corrections Issued RAUL OLAGI
Green Building Final 8/26/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 8/26/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 8/26/2022 Approved RAUL OLAGI
Final 9/8/2022 OK to Issue CofO RAUL OLAGI
Service/Power Release 9/8/2022 Approved RAUL OLAGI