8133 N GENESTA AVE 91406
Certificate Information: 8133 N GENESTA AVE 91406
- Application / Permit
- 21014-20000-05014
- Plan Check / Job No.
- B21VN13498
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD NEW 18'-0" x 15'-0" AND INTERIOR REMODEL TO THE (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/22/2021
- Issuing Office
- Current Status
- CofO Issued on 9/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | ALFRED RAMIREZ |
| Corrections Issued | 10/7/2021 | ALFRED RAMIREZ |
| Issued | 10/22/2021 | APPLICANT |
| Building Plans Picked Up | 10/25/2021 | APPLICANT |
| CofO in Progress | 9/9/2022 | RAUL OLAGI |
| CofO Issued | 9/12/2022 | MICHAEL SMITH |
| Permit Finaled | 9/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/7/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | 20301 VENTURA BLVD #222 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/11/2022 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 3/15/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 4/8/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 4/20/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 4/21/2022 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 5/12/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/12/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/12/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/19/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 5/19/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/19/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/19/2022 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 5/27/2022 | Approved | RAUL OLAGI |
| Insulation | 5/27/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/27/2022 | Approved | RAUL OLAGI |
| Shower Pan | 5/27/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 6/3/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/6/2022 | Approved | ALAN MORELOS |
| Rough-Elec/Plmb/HVAC | 8/17/2022 | Partial Inspection | RAUL OLAGI |
| Special/Order Compliance | 8/17/2022 | Corrections Issued | RAUL OLAGI |
| Final | 8/26/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 8/26/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/26/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 8/26/2022 | Approved | RAUL OLAGI |
| Final | 9/8/2022 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 9/8/2022 | Approved | RAUL OLAGI |