13435 W HARTLAND ST 91405

Certificate Information: 13435 W HARTLAND ST 91405

Application / Permit
21014-20000-05011
Plan Check / Job No.
B21VN13489
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
15'-10" X 13'-2", 186.5 SQ. FT. ADDITION TO THE (E) SINGLE FAMILY DWELLING. ALL WORK SHALL CONFORM TO THE WFPP.
Permit Issued
Issued on 11/2/2021
Issuing Office
Current Status
CofO Issued on 1/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2021 APPLICANT
Assigned to Plan Check Engineer 10/5/2021 COLIN LOREDO
Corrections Issued 10/7/2021 COLIN LOREDO
Building Plans Picked Up 10/15/2021 APPLICANT
Plan Check Approved 11/2/2021 COLIN LOREDO
Issued 11/2/2021 APPLICANT
CofO in Progress 5/24/2023 KIRK SANDERS
CofO Issued 1/4/2024 RUBEN SALAS
Permit Finaled 1/4/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/18/2021 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 10/18/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 10/18/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/10/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/3/2022 Partial Approval CHRISTOPHE COCHRAN
Insulation 1/3/2022 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 1/3/2022 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/7/2022 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 1/7/2022 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Partial Approval CHRISTOPHE COCHRAN
Pre-Inspection 1/31/2022 Not Ready for Inspection JACK KARGODORIAN
Underground Mechanical 2/1/2022 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 2/8/2022 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/11/2022 Not Ready for Inspection MATT KELLERMAN
Rough-Elec/Plmb/HVAC 2/11/2022 Partial Approval MATT KELLERMAN
PLUMBING-Rough 2/16/2022 Approved CHRISTOPHE COCHRAN
Rough-Elec/Plmb/HVAC 2/16/2022 Approved CHRISTOPHE COCHRAN
Wood Frame 2/16/2022 Approved CHRISTOPHE COCHRAN
Insulation 2/22/2022 Approved JACK KARGODORIAN
Drywall Nailing 3/30/2022 Approved ASHLEY THOMPSON
Shower Pan 3/30/2022 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 4/11/2022 Partial Approval CALEB MEISTER
Shower Pan 4/11/2022 Approved CALEB MEISTER
ELECTRICAL-Final 7/21/2022 Not Ready for Inspection RAFAEL CORTES
ELECTRICAL-Final 12/20/2022 Corrections Issued KIRK SANDERS
PLUMBING-Final 12/20/2022 Approved KIRK SANDERS
ELECTRICAL-Final 5/8/2023 Approved KIRK SANDERS
Final 5/8/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 5/23/2023 Approved KIRK SANDERS
Final 5/23/2023 OK to Issue CofO KIRK SANDERS
Green Building Final 5/23/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Approved KIRK SANDERS
Smoke Detectors 5/23/2023 Approved KIRK SANDERS