9219 W SAWYER ST 90035
Certificate Information: 9219 W SAWYER ST 90035
- Application / Permit
- 21014-20000-05008
- Plan Check / Job No.
- B21VN13475
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY SINGLE FAMILY DWELLING EXCEPT FOR 1' LF AT WEST SIDE AND BUILD AN IRREGULAR SHAPED 60'5" X 45'-1" TWO STORY SINGLE FAMILY DWELLING WITH AN ATTACHED TWO CAR GARAGE, BASEMENT, NFPA-13D FIRE SPRINKLERS THROUGHOUT REQUIRED, ALL WORK PER ENGINEERING SEE COMMENTS
- Permit Issued
- Issued on 6/6/2022
- Issuing Office
- Current Status
- CofO Issued on 6/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 11/12/2021 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 11/19/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/22/2021 | APPLICANT |
| Applicant returned to address corrections | 12/13/2021 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 2/14/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 2/16/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 4/5/2022 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 5/13/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 5/23/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 6/6/2022 | APPLICANT |
| CofO in Progress | 6/24/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 6/24/2024 | DANIEL ORRANTE |
| CofO Issued | 6/24/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/24/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/3/2021 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 1/28/2022 | SARAH YOUSSEF |
| Trees in Parkway | Cleared | 2/8/2022 | ADALBERTO VERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 2/15/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/15/2022 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 3/15/2022 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 4/5/2022 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 4/5/2022 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Inhance Construction Inc; Lic. No.: 1073871-B | 7257 BEVERLY RD STE 205 LOS ANGELES, CA 90036 |
| Engineer | Haro,, Ruben; Lic. No.: GE2990 | 555 N LANTANA ST STE 492 CAMARILLO, CA 93010 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/26/2022 | Corrections Issued | STEPHANIE SWANSON |
| Pre-Inspection | 8/22/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 10/12/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 12/16/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/2/2023 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Barrier | 2/2/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Subgrade | 2/2/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2023 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Wood Construction | 4/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Reinf. Concrete | 4/18/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 5/12/2023 | Conditional Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 5/19/2023 | Approved | JEREMY TODD |
| Green Building Rough | 5/19/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Barrier | 5/19/2023 | Approved | JEREMY TODD |
| METHANE-Rough | 5/19/2023 | Approved | JEREMY TODD |
| METHANE-Subgrade | 5/19/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 8/2/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/2/2023 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/9/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/9/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/14/2023 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 8/14/2023 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/22/2023 | Approved | TEMISTOCLES CAAL |
| Insulation | 8/24/2023 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 8/30/2023 | Corrections Issued | CLAYTON GRAHAM |
| Drywall Nailing | 9/5/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Drywall Nailing | 9/7/2023 | Approved | CLAYTON GRAHAM |
| Shower Pan | 9/7/2023 | Approved | CLAYTON GRAHAM |
| Verify Sprinkler Sign Off | 9/7/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 9/18/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 2/15/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 2/16/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 2/16/2024 | Approved | OGANES TARAKHCHYAN |
| Sewer | 2/20/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 2/23/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Gas Test | 2/26/2024 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 2/26/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 2/27/2024 | Approved | KENNETH NAGLE |
| PLUMBING-Final | 3/19/2024 | Approved | OGANES TARAKHCHYAN |
| Grading Pre-Inspection | 4/12/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/31/2024 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 5/31/2024 | Approved | MEL KHACHATOURIAN |
| Final | 5/31/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| Green Building Final | 5/31/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 5/31/2024 | Approved | MEL KHACHATOURIAN |