4802 N SALOMA AVE 91403

Certificate Information: 4802 N SALOMA AVE 91403

Application / Permit
21014-20000-05007
Plan Check / Job No.
B21VN13472
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL EXISTING SINGLE FAMILY DWELLING; 20'-4" X 19'-5" FIRST FLOOR ADDITION; 60'-11" X 29'-11" IRREGULAR SHAPED ADDITION; ADD 178 SQ FT TO THE GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/4/2022
Issuing Office
Current Status
CofO Issued on 12/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 SELLA BENYAMIN
Corrections Issued 11/2/2021 SELLA BENYAMIN
Quality Review Completed 11/9/2021 STEVEN KIM
Building Plans Picked Up 11/12/2021 APPLICANT
Plan Check Approved 4/23/2022 SELLA BENYAMIN
Issued 5/4/2022 APPLICANT
CofO in Progress 10/31/2023 CHRISTOPHE COCHRAN
No Progress 11/6/2023 THOMAS FINNILA
CofO in Progress 11/6/2023 THOMAS FINNILA
CofO in Progress 11/11/2023 JUAN VALENZUELA
Permit Finaled 12/29/2023 RUBEN SALAS
CofO Issued 12/29/2023 RUBEN SALAS
Permit Finaled 12/29/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/18/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 11/18/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 2/3/2022 JORGE MEJIA LEMUS
Hydrant and Access approval Cleared 2/14/2022 JOHN CONNEALLY
Permit Cleared 2/24/2022 DAGOVERTO GUERRERO
Trees in Parkway Cleared 3/2/2022 ADALBERTO VERA
Roof/Waste drainage to street Cleared 3/7/2022 CARLOS AGUILERA

Contact Information

Contractor Bas Associates Construction; Lic. No.: 610162-B 6821 PLATT AVE      WEST HILLS, CA 91307
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/19/2022 Corrections Issued JACK KARGODORIAN
Deputy Drilled-In Anchors 6/10/2022 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 6/30/2022 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 6/30/2022 Not Ready for Inspection JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 7/2/2022 Approved ALAN MORELOS
PLUMBING-Rough 7/2/2022 Corrections Issued ALAN MORELOS
BUILDING-Rough-Frame 7/22/2022 Corrections Issued MISAEL ESPARZA
Sewer 7/22/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 7/23/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 10/11/2022 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 10/11/2022 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 10/13/2022 Partial Approval THOMAS FINNILA
PLUMBING-Rough 10/27/2022 Approved CALEB MEISTER
Wood Frame 10/27/2022 Corrections Issued CALEB MEISTER
Deputy Wood Construction 10/28/2022 Conditional Approval MICHAEL SMITH
Wood Frame 11/2/2022 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 11/8/2022 Corrections Issued THOMAS FINNILA
HVAC-Rough 11/8/2022 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 11/17/2022 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Approved DAVID ANDERSON
Green Building Rough 11/17/2022 Not Ready for Inspection DAVID ANDERSON
HVAC-Rough 11/17/2022 Corrections Issued DAVID ANDERSON
MERV13>=Rough 11/17/2022 Approved DAVID ANDERSON
Special/Order Compliance 11/17/2022 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 11/28/2022 Approved THOMAS FINNILA
HVAC-Rough 11/28/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 12/9/2022 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 1/17/2023 Partial Approval THOMAS FINNILA
Green Building Rough 1/17/2023 Approved THOMAS FINNILA
Insulation 2/8/2023 Corrections Issued THOMAS FINNILA
Insulation 2/10/2023 Approved THOMAS FINNILA
Drywall Nailing 2/17/2023 Approved THOMAS FINNILA
Drywall Nailing 2/23/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 3/23/2023 Not Ready for Inspection THOMAS FINNILA
Shower Pan 3/23/2023 Conditional Approval THOMAS FINNILA
Interior/Exterior Lathing 4/10/2023 Approved THOMAS FINNILA
ELECTRICAL-Final 8/2/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 8/2/2023 Not Ready for Inspection THOMAS FINNILA
Service/Power Release 8/2/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 9/1/2023 Corrections Issued THOMAS FINNILA
HVAC-Final 9/1/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 9/1/2023 Corrections Issued THOMAS FINNILA
Service/Power Release 9/1/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 9/19/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 9/19/2023 Not Ready for Inspection MISAEL ESPARZA
Final 9/19/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/19/2023 Approved MISAEL ESPARZA
Green Building Final 9/19/2023 Approved MISAEL ESPARZA
HVAC-Final 9/19/2023 Approved MISAEL ESPARZA
MERV13>=Final 9/19/2023 Approved MISAEL ESPARZA
PLUMBING-Final 9/19/2023 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 9/19/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 9/19/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 9/22/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 9/22/2023 Approved THOMAS FINNILA
PLUMBING-Final 9/22/2023 Approved THOMAS FINNILA
Final 10/10/2023 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/10/2023 SGSOV Approved THOMAS FINNILA
Final 10/28/2023 Corrections Issued RAUL OLAGI
Final 10/28/2023 Off-Hour Fees Due
Final 10/31/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 11/6/2023 Corrections Issued THOMAS FINNILA
Final 11/10/2023 OK to Issue CofO JUAN VALENZUELA
Service/Power Release 11/13/2023 Approved JUAN VALENZUELA