12317 W OSBORNE PL 91331
Certificate Information: 12317 W OSBORNE PL 91331
- Application / Permit
- 21014-20000-05002
- Plan Check / Job No.
- B21VN13452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY GROUND FLOOR ADDITION (69'-7"x20-11"), 1196 SQFT TO REAR OF (E) SFD W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 7/15/2022
- Issuing Office
- Current Status
- Issued on 7/15/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | PETER MOSESIAN |
| Corrections Issued | 11/7/2021 | PETER MOSESIAN |
| Quality Review Completed | 11/19/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/22/2021 | APPLICANT |
| Applicant returned to address corrections | 2/24/2022 | PETER MOSESIAN |
| Applicant returned to address corrections | 6/29/2022 | PETER MOSESIAN |
| Plan Check Approved | 7/15/2022 | PETER MOSESIAN |
| Issued | 7/15/2022 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/28/2021 | DAGOVERTO GUERRERO |
| ZA Case | Cleared | 3/29/2022 | PABLO ESTRADA |
| Clean Up Green Up | Cleared | 4/18/2022 | PABLO ESTRADA |
| Low Impact Development | Cleared | 6/20/2022 | LONDY ALVARADO |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/7/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Sarahang Construction Inc; Lic. No.: 897724-B | 39312 DUNBAR PALMDALE, CA 93551 |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: C53256 | 11607 AMESTOY AVE GRANADA HILLS, CA 91344 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/8/2022 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 10/24/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/24/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/12/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/12/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 12/12/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 12/12/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/12/2022 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 12/14/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/10/2023 | Approved | MICHEL ABAJAN |
| Insulation | 1/10/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/10/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 1/25/2023 | Partial Approval | MATTHEW NELSON |