22916 W GAULT ST 91307

Certificate Information: 22916 W GAULT ST 91307

Application / Permit
21014-20000-04974
Plan Check / Job No.
B21VN13395
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) 20' X 20' ATTACHED CARPORT AND ADD 20' X 24' 2-CAR GARAGE TO (E) SFD. ALL WORK PER DESIGN.
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
CofO Issued on 10/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2021 APPLICANT
Assigned to Plan Check Engineer 10/4/2021 RAPHAEL ROSAS
Corrections Issued 10/4/2021 RAPHAEL ROSAS
Applicant returned to address corrections 11/18/2021 RAPHAEL ROSAS
Plan Check Approved 4/3/2022 RAPHAEL ROSAS
Building Plans Picked Up 4/5/2022 APPLICANT
Issued 4/25/2022 APPLICANT
CofO in Progress 9/29/2022 CHRIS CHRISTENSEN
Permit Finaled 10/3/2022 MICHAEL SMITH
CofO Issued 10/3/2022 MICHAEL SMITH
Permit Finaled 10/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/8/2021 JOSE DUARTE-DIAZ
Low Impact Development Cleared 3/21/2022 TA ANH
Roof/Waste drainage to street Cleared 4/2/2022 CARLOS AGUILERA

Contact Information

Architect Blaugrund,, Charles I; Lic. No.: C25792 14994 MARQUETTE STREET      MOORPARK, CA 93021
Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/1/2022 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/27/2022 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Approved PETER FOLLING
Green Building Rough 6/27/2022 Not Ready for Inspection PETER FOLLING
Green Building Final 6/30/2022 Not Ready for Inspection DAVID SANDOVAL
Insulation 6/30/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 6/30/2022 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 7/6/2022 Approved PETER FOLLING
Green Building Rough 7/6/2022 Approved PETER FOLLING
Interior/Exterior Lathing 7/6/2022 Approved PETER FOLLING
ELECTRICAL-Final 9/22/2022 Approved CHRIS CHRISTENSEN
Final 9/22/2022 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 9/22/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 9/22/2022 Approved CHRIS CHRISTENSEN