3764 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3764 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 21014-20000-04964
- Plan Check / Job No.
- B21VN13370
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE 1170 SF OF (E) SFD EXCEPT FOR SOUTHWESTERN 13' WALL & FOOTING TO REMAIN. REBUILD 38' X 61'-1" 2-STORY SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/1/2022
- Issuing Office
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | RAPHAEL ROSAS |
| Corrections Issued | 10/19/2021 | RAPHAEL ROSAS |
| Quality Review Completed | 10/21/2021 | STEVEN KIM |
| Applicant returned to address corrections | 3/23/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/11/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| Applicant returned to address corrections | 5/24/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 7/27/2022 | RAPHAEL ROSAS |
| Issued | 8/1/2022 | APPLICANT |
| CofO in Progress | 11/29/2023 | TEMISTOCLES CAAL |
| CofO in Progress | 11/30/2023 | MICHAEL PELHAM |
| CofO in Progress | 12/1/2023 | RICHARD STEINBACH |
| Permit Finaled | 12/5/2023 | DANIEL ORRANTE |
| CofO Issued | 12/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 10/27/2021 | DANG NGUYEN |
| Address approval | Cleared | 11/1/2021 | DINAH GARIN |
| Permit | Cleared | 11/2/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 11/3/2021 | SAUL GARCIA |
| Low Impact Development | Cleared | 12/10/2021 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 12/13/2021 | SAUL GARCIA |
| Hydrant and Access approval | Cleared | 1/25/2022 | KURT CORRAL |
| Trees in Parkway | Cleared | 3/4/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 5/24/2022 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 5/24/2022 | RAPHAEL ROSAS |
Contact Information
| Contractor | Gaudenti & Sons Corporation; Lic. No.: 283650-B | 231 VISTA DEL MAR REDONDO BEACH, CA 90277 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/4/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/30/2022 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 9/2/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 9/12/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 9/12/2022 | Not Ready for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 9/14/2022 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 9/26/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/9/2023 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 1/9/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/9/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 2/3/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Deck | 3/31/2023 | Partial Approval | KENNETH NAGLE |
| Gas Test | 4/20/2023 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 4/21/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 4/21/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 5/2/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 5/2/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 5/2/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/2/2023 | Partial Approval | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 5/2/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 5/5/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 5/10/2023 | Partial Approval | JOHNNY MIRANDA |
| Gas Test | 5/17/2023 | Partial Approval | JOHNNY MIRANDA |
| Sewer | 5/17/2023 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 6/9/2023 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 7/10/2023 | Approved | JESUS PINEDA |
| Shower Pan | 7/10/2023 | Approved | JESUS PINEDA |
| Gas Test | 10/5/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 11/8/2023 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 11/14/2023 | Corrections Issued | JESUS PINEDA |
| Service/Power Release | 11/14/2023 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 11/16/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/16/2023 | Off-Hour Fees Due | |
| Service/Power Release | 11/16/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 11/22/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 11/22/2023 | Off-Hour Fees Due | |
| Final | 11/22/2023 | Conditional Approval | TEMISTOCLES CAAL |
| Final | 11/22/2023 | Off-Hour Fees Due | |
| Green Building Final | 11/22/2023 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 11/22/2023 | Off-Hour Fees Due | |
| HVAC-Final | 11/22/2023 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 11/22/2023 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 11/22/2023 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 11/22/2023 | Off-Hour Fees Due |