13979 W HERRON ST 91342

Certificate Information: 13979 W HERRON ST 91342

Application / Permit
21014-20000-04962
Plan Check / Job No.
B21VN13359
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 18' DETACHED CARPORT AND ADD 16' X 30' IRREGULAR SHAPE TO CREATE (N) DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK EPR WFPP.
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 7/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2021 APPLICANT
Assigned to Plan Check Engineer 10/4/2021 RAPHAEL ROSAS
Corrections Issued 10/4/2021 RAPHAEL ROSAS
Applicant returned to address corrections 10/28/2021 RAPHAEL ROSAS
Plan Check Approved 11/19/2021 RAPHAEL ROSAS
Issued 12/2/2021 APPLICANT
Building Plans Picked Up 12/3/2021 APPLICANT
CofO in Progress 7/8/2022 ARAM AVEDISIAN
Permit Finaled 7/16/2022 MICHAEL SMITH
CofO Issued 7/16/2022 MICHAEL SMITH
Permit Finaled 7/16/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/12/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 10/12/2021 CARLOS AGUILERA
Sewer availability Cleared 10/13/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/14/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/21/2021 Partial Inspection JOHN HAYES
Footing/Foundation/Slab 1/27/2022 Corrections Issued JOHN HAYES
PLUMBING-Rough 1/27/2022 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 2/2/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 2/2/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Partial Approval JOHN HAYES
ELECTRICAL-Rough 3/9/2022 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 3/9/2022 Approved MICHEL ABAJAN
Sewer 3/9/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 3/9/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 3/23/2022 Corrections Issued MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Approved MICHAEL TEMPLE
Green Building Rough 3/23/2022 Not Ready for Inspection MICHAEL TEMPLE
HVAC-Rough 3/23/2022 Corrections Issued MICHAEL TEMPLE
Sewer 3/23/2022 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 4/5/2022 Approved JOHN HAYES
Green Building Rough 4/5/2022 Approved JOHN HAYES
Interior/Exterior Lathing 4/5/2022 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 4/5/2022 Approved JOHN HAYES
Shower Pan 4/5/2022 Approved JOHN HAYES
Insulation 4/8/2022 Approved JOHN HAYES
Interior/Exterior Lathing 4/8/2022 Approved JOHN HAYES
Drywall Nailing 4/20/2022 Approved JOHN HAYES
Gas Test 5/5/2022 Approved JOHN HAYES
Underground Mechanical 5/5/2022 Approved JOHN HAYES
Final 6/30/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 6/30/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 6/30/2022 Approved ARAM AVEDISIAN
Final 7/8/2022 OK to Issue CofO ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/8/2022 SGSOV Approved ARAM AVEDISIAN