13979 W HERRON ST 91342
Certificate Information: 13979 W HERRON ST 91342
- Application / Permit
- 21014-20000-04962
- Plan Check / Job No.
- B21VN13359
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 18' DETACHED CARPORT AND ADD 16' X 30' IRREGULAR SHAPE TO CREATE (N) DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK EPR WFPP.
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- CofO Issued on 7/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/4/2021 | RAPHAEL ROSAS |
| Corrections Issued | 10/4/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/28/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 11/19/2021 | RAPHAEL ROSAS |
| Issued | 12/2/2021 | APPLICANT |
| Building Plans Picked Up | 12/3/2021 | APPLICANT |
| CofO in Progress | 7/8/2022 | ARAM AVEDISIAN |
| Permit Finaled | 7/16/2022 | MICHAEL SMITH |
| CofO Issued | 7/16/2022 | MICHAEL SMITH |
| Permit Finaled | 7/16/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/12/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/13/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/21/2021 | Partial Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 1/27/2022 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 1/27/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 2/2/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/2/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 3/9/2022 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 3/9/2022 | Approved | MICHEL ABAJAN |
| Sewer | 3/9/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 3/9/2022 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/23/2022 | Corrections Issued | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2022 | Approved | MICHAEL TEMPLE |
| Green Building Rough | 3/23/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| HVAC-Rough | 3/23/2022 | Corrections Issued | MICHAEL TEMPLE |
| Sewer | 3/23/2022 | Approved | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 4/5/2022 | Approved | JOHN HAYES |
| Green Building Rough | 4/5/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 4/5/2022 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 4/5/2022 | Approved | JOHN HAYES |
| Shower Pan | 4/5/2022 | Approved | JOHN HAYES |
| Insulation | 4/8/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 4/8/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 4/20/2022 | Approved | JOHN HAYES |
| Gas Test | 5/5/2022 | Approved | JOHN HAYES |
| Underground Mechanical | 5/5/2022 | Approved | JOHN HAYES |
| Final | 6/30/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 6/30/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 6/30/2022 | Approved | ARAM AVEDISIAN |
| Final | 7/8/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | SGSOV Approved | ARAM AVEDISIAN |