13573 N ELDRIDGE AVE 91342

Certificate Information: 13573 N ELDRIDGE AVE 91342

Application / Permit
21014-20000-04956
Plan Check / Job No.
B21VN13343
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 24'-1" X 19'-7" (351 SQ. FT) IRREGULAR SHAPED ADDITION TO THE REAR OF THE (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/5/2021
Issuing Office
Current Status
CofO Issued on 3/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2021 APPLICANT
Assigned to Plan Check Engineer 10/1/2021 OMAR GARNICA
Corrections Issued 10/1/2021 OMAR GARNICA
Plan Check Approved 11/1/2021 OMAR GARNICA
Building Plans Picked Up 11/2/2021 APPLICANT
Issued 11/5/2021 APPLICANT
CofO in Progress 2/19/2022 MICHAEL TEMPLE
Permit Finaled 3/4/2022 MICHAEL SMITH
CofO Issued 3/4/2022 MICHAEL SMITH
Permit Finaled 3/4/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/13/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/14/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Armando; Lic. No.: C83911 121 N VAIL AVE      MONTEBELLO, CA 90640

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/18/2021 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 11/30/2021 Approved MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 12/10/2021 Conditional Approval JESUS RODRIGUEZ
PLUMBING-Rough 12/10/2021 Corrections Issued JESUS RODRIGUEZ
Sewer 12/10/2021 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/5/2022 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 1/10/2022 Approved Pending GreenApproval JOHN HAYES
Green Building Rough 1/10/2022 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 1/10/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Approved JOHN HAYES
Insulation 1/18/2022 Approved JOHN HAYES
Interior/Exterior Lathing 1/18/2022 Partial Approval JOHN HAYES
Shower Pan 1/18/2022 Approved JOHN HAYES
Drywall Nailing 1/24/2022 Approved JOHN HAYES
Interior/Exterior Lathing 1/24/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 2/15/2022 Not Ready for Inspection JOHN HAYES
Final 2/15/2022 Corrections Issued JOHN HAYES
Green Building Final 2/15/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/15/2022 SGSOV Not Ready JOHN HAYES
Smoke Detectors 2/15/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 2/18/2022 Approved MICHAEL TEMPLE
Final 2/18/2022 OK to Issue CofO MICHAEL TEMPLE
Green Building Final 2/18/2022 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV Approved MICHAEL TEMPLE
Smoke Detectors 2/18/2022 Approved MICHAEL TEMPLE