4944 N DOBKIN AVE 91356

Certificate Information: 4944 N DOBKIN AVE 91356

Application / Permit
21014-20000-04933
Plan Check / Job No.
B21VN13286
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. NEW ADDITION AT REAR OF (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 8/29/2022
Issuing Office
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2021 APPLICANT
Assigned to Plan Check Engineer 10/6/2021 KEVIN MORALES
Corrections Issued 10/6/2021 KEVIN MORALES
Applicant returned to address corrections 10/25/2021 KEVIN MORALES
Applicant returned to address corrections 5/12/2022 KEVIN MORALES
Plan Check Approved 6/16/2022 KEVIN MORALES
Issued 8/29/2022 APPLICANT
CofO in Progress 4/8/2024 JOHN KIDWELL
Permit Finaled 4/15/2024 JOHN JANSON
CofO Issued 4/15/2024 JOHN JANSON
Permit Finaled 4/15/2024 JOHN JANSON

Permit Application Clearance Information

Sewer availability Cleared 10/13/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/25/2021 CARLOS AGUILERA
Low Impact Development Cleared 4/21/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 5/3/2022 ABDULLAH SADOZAI
Grading Pre-Inspection Cleared 5/12/2022 SERGIO VALENZUELA
GPI Written Notices Cleared 6/16/2022 KEVIN MORALES

Contact Information

Contractor Alec Julien Construction; Lic. No.: 1093621-B 825 S MYRTLE AVE APT 409      MONROVIA, CA 91016

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/15/2022 Partial Approval DAVID SANDOVAL
PLUMBING-Rough 9/15/2022 Corrections Issued DAVID SANDOVAL
Sewer 9/15/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 9/21/2022 Partial Inspection DAVID SANDOVAL
PLUMBING-Rough 9/21/2022 Partial Approval DAVID SANDOVAL
Sewer 9/21/2022 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 9/28/2022 Approved DAVID SANDOVAL
Deputy Wood Construction 12/6/2022 Conditional Approval MORRIS JACKSON
ELECTRICAL-Rough 12/7/2022 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Partial Approval DAVID SANDOVAL
Gas Test 12/7/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 12/7/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 12/7/2022 Not Ready for Inspection DAVID SANDOVAL
Sewer 12/7/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Approved DAVID SCANTLIN
Gas Test 12/13/2022 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 12/13/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 12/19/2022 Approved DAVID SANDOVAL
Green Building Rough 12/19/2022 Approved DAVID SANDOVAL
Insulation 12/19/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 12/19/2022 Partial Approval DAVID SANDOVAL
Shower Pan 12/19/2022 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 12/19/2022 Approved DAVID SANDOVAL
Drywall Nailing 12/23/2022 Partial Approval JESUS PINEDA
Interior/Exterior Lathing 12/23/2022 Approved JESUS PINEDA
Drywall Nailing 12/27/2022 Approved JESUS PINEDA
Final 8/16/2023 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/16/2023 SGSOV Approved SEAN HAUPT
Smoke Detectors 8/16/2023 Approved SEAN HAUPT
Final 4/3/2024 OK to Issue CofO JOHN KIDWELL