11661 N TRIPOLI AVE 91342
Certificate Information: 11661 N TRIPOLI AVE 91342
- Application / Permit
- 21014-20000-04896
- Plan Check / Job No.
- B21VN13149
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL, ADD NEW (52'-2"x 35'-1") 2ND STORY, REMOVE AND REPLACE PATIO COVER WITH DECK ABOVE ALL WORK PER ENGINEERING NFPA-13D AUTO FIRESPRINKLER THROUGHOUT
- Permit Issued
- Issued on 12/14/2022
- Issuing Office
- Valley
- Current Status
- Issued on 12/14/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | TROY DEGUZMAN |
| Corrections Issued | 11/1/2021 | TROY DEGUZMAN |
| Quality Review Completed | 11/12/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/15/2021 | APPLICANT |
| Plan Check Approved | 12/14/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 12/14/2022 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 11/1/2021 | TROY DEGUZMAN |
| Sewer availability | Cleared | 1/13/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 1/21/2022 | VASIL MIHALEV |
| Hydrant and Access approval | Cleared | 3/30/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 4/8/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/22/2022 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 12/7/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/29/2023 | Partial Approval | WILLIAM MICHALAK |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 8/18/2023 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 1/30/2024 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 2/20/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2024 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 2/20/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/20/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/19/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/19/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 3/19/2024 | Approved | MICHEL ABAJAN |
| Gas Test | 7/26/2024 | Approved | MICHEL ABAJAN |
| Insulation | 7/26/2024 | Conditional Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/26/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 8/12/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/5/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/5/2024 | Approved | MISAEL ESPARZA |