2830 S MALCOLM AVE 90064
Certificate Information: 2830 S MALCOLM AVE 90064
- Application / Permit
- 21014-20000-04837
- Plan Check / Job No.
- B21VN13008
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 17'5" X 12'2" IRREGULAR SHAPED ADDITION TO CREATE NEW BATHROOM AND W..I.C AMD BEDROOM CLOSET , NEW 7'2" X 1'9" ADDITION TO (E) SFD TO ENLARGE THE KITCHEN , AND INTERIOR REMODEL TO THE (E) SFD TO REMODEL (3) BEDROOMS , KITCHEN, LIVING ROOM, BATHROOM, CREATE NEW LAUNDRY ROOM , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/23/2021
- Issuing Office
- Current Status
- CofO Issued on 2/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2021 | RARES BODEA |
| Corrections Issued | 9/28/2021 | RARES BODEA |
| Building Plans Picked Up | 10/1/2021 | APPLICANT |
| Applicant returned to address corrections | 11/22/2021 | RARES BODEA |
| Plan Check Approved | 11/23/2021 | RARES BODEA |
| Issued | 11/23/2021 | APPLICANT |
| CofO in Progress | 11/16/2022 | JOHNNY MIRANDA |
| Permit Finaled | 2/12/2023 | DANIEL ORRANTE |
| CofO Issued | 2/12/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/12/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/12/2021 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2021 | DINAH GARIN |
| Specific Plan | Cleared | 10/27/2021 | PETE EYRE |
| Roof/Waste drainage to street | Cleared | 10/28/2021 | DINAH GARIN |
Contact Information
| Contractor | Elite Power Remodeling And Design; Lic. No.: 1053184-B | 22919 STYLES STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/9/2022 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 3/16/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 4/12/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/20/2022 | Partial Approval | RICHARD STEINBACH |
| HVAC-Rough | 6/20/2022 | Corrections Issued | RICHARD STEINBACH |
| PLUMBING-Rough | 6/20/2022 | Corrections Issued | RICHARD STEINBACH |
| Wood Frame | 6/20/2022 | Corrections Issued | RICHARD STEINBACH |
| Deputy Wood Construction | 6/22/2022 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/23/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 6/27/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 6/27/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/27/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 7/1/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 7/1/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 7/1/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 7/1/2022 | Partial Approval | JOHNNY MIRANDA |
| MERV13>=Rough | 7/1/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 7/14/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 7/14/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Shower Pan | 7/28/2022 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 10/31/2022 | Corrections Issued | JOHNNY MIRANDA |
| Final | 10/31/2022 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 10/31/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 10/31/2022 | Approved | JOHNNY MIRANDA |
| MERV13>=Final | 10/31/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 10/31/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 10/31/2022 | Approved | JOHNNY MIRANDA |
| Final | 11/10/2022 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 11/16/2022 | Approved | JOHNNY MIRANDA |
| Final | 11/16/2022 | OK to Issue CofO | JOHNNY MIRANDA |