2830 S MALCOLM AVE 90064

Certificate Information: 2830 S MALCOLM AVE 90064

Application / Permit
21014-20000-04837
Plan Check / Job No.
B21VN13008
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 17'5" X 12'2" IRREGULAR SHAPED ADDITION TO CREATE NEW BATHROOM AND W..I.C AMD BEDROOM CLOSET , NEW 7'2" X 1'9" ADDITION TO (E) SFD TO ENLARGE THE KITCHEN , AND INTERIOR REMODEL TO THE (E) SFD TO REMODEL (3) BEDROOMS , KITCHEN, LIVING ROOM, BATHROOM, CREATE NEW LAUNDRY ROOM , ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/23/2021
Issuing Office
Current Status
CofO Issued on 2/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2021 APPLICANT
Assigned to Plan Check Engineer 9/28/2021 RARES BODEA
Corrections Issued 9/28/2021 RARES BODEA
Building Plans Picked Up 10/1/2021 APPLICANT
Applicant returned to address corrections 11/22/2021 RARES BODEA
Plan Check Approved 11/23/2021 RARES BODEA
Issued 11/23/2021 APPLICANT
CofO in Progress 11/16/2022 JOHNNY MIRANDA
Permit Finaled 2/12/2023 DANIEL ORRANTE
CofO Issued 2/12/2023 DANIEL ORRANTE
Permit Finaled 2/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/12/2021 BRIAN MILLER
Eng Process Fee Ord 176,300 Cleared 10/15/2021 DINAH GARIN
Specific Plan Cleared 10/27/2021 PETE EYRE
Roof/Waste drainage to street Cleared 10/28/2021 DINAH GARIN

Contact Information

Contractor Elite Power Remodeling And Design; Lic. No.: 1053184-B 22919 STYLES STREET      WOODLAND HILLS, CA 91367

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/9/2022 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 3/16/2022 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/12/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 4/12/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/13/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 6/20/2022 Partial Approval RICHARD STEINBACH
HVAC-Rough 6/20/2022 Corrections Issued RICHARD STEINBACH
PLUMBING-Rough 6/20/2022 Corrections Issued RICHARD STEINBACH
Wood Frame 6/20/2022 Corrections Issued RICHARD STEINBACH
Deputy Wood Construction 6/22/2022 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 6/23/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 6/27/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Approved JOHNNY MIRANDA
HVAC-Rough 6/27/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 6/27/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 7/1/2022 Approved JOHNNY MIRANDA
Green Building Rough 7/1/2022 Approved JOHNNY MIRANDA
Insulation 7/1/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 7/1/2022 Partial Approval JOHNNY MIRANDA
MERV13>=Rough 7/1/2022 Approved JOHNNY MIRANDA
Drywall Nailing 7/14/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 7/14/2022 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 7/28/2022 Approved MICHAEL PELHAM
ELECTRICAL-Final 10/31/2022 Corrections Issued JOHNNY MIRANDA
Final 10/31/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 10/31/2022 Approved JOHNNY MIRANDA
HVAC-Final 10/31/2022 Approved JOHNNY MIRANDA
MERV13>=Final 10/31/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 10/31/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 10/31/2022 Approved JOHNNY MIRANDA
Final 11/10/2022 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 11/10/2022 SGSOV Approved JOHNNY MIRANDA
ELECTRICAL-Final 11/16/2022 Approved JOHNNY MIRANDA
Final 11/16/2022 OK to Issue CofO JOHNNY MIRANDA