15837-15839 W SIMONDS ST 91344
Certificate Information: 15837-15839 W SIMONDS ST 91344
- Application / Permit
- 21014-20000-04832
- Plan Check / Job No.
- B21VN12997
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- JADU Conversion From Existing Garage ATTACHED TO (E) SFD
- Permit Issued
- Issued on 1/31/2022
- Issuing Office
- Current Status
- CofO Issued on 3/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2021 | CARLOS MONTES |
| Corrections Issued | 9/27/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 10/29/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/3/2021 | CARLOS MONTES |
| Building Plans Picked Up | 12/20/2021 | APPLICANT |
| Plan Check Approved | 1/6/2022 | CARLOS MONTES |
| Issued | 1/31/2022 | APPLICANT |
| CofO in Progress | 12/12/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 3/28/2024 | DANIEL ORRANTE |
| CofO Issued | 3/28/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/28/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/6/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2022 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 6/14/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/15/2022 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 7/15/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/26/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/30/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/30/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/3/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/3/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/3/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/3/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 3/15/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/11/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| Shower Pan | 4/11/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/13/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 4/13/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/5/2023 | Approved | JENNIFER RABUCHIN |
| Final | 10/5/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/5/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 10/5/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 10/5/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/11/2023 | Approved | JENNIFER RABUCHIN |
| Final | 12/11/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 12/11/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 12/11/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/11/2023 | Approved | JENNIFER RABUCHIN |