13271 W DYER ST 91342
Certificate Information: 13271 W DYER ST 91342
- Application / Permit
- 21014-20000-04829
- Plan Check / Job No.
- B21VN12995
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU addition. Converting a garage into an ADU and addition
- Permit Issued
- Issued on 6/7/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 11/5/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/16/2021 | HERNAN ARREOLA |
| Plan Check Approved | 6/6/2022 | ARSALAN SHABESTARI |
| Issued | 6/7/2022 | APPLICANT |
| CofO in Progress | 12/5/2022 | ARAM AVEDISIAN |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 2/10/2022 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 2/10/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 2/10/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/11/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 2/23/2022 | VASIL MIHALEV |
| Hydrant and Access approval | Cleared | 3/16/2022 | CINDY JOSSELYN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/28/2022 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/28/2022 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 7/5/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/5/2022 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/25/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/25/2022 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 7/25/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 7/25/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/1/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/1/2022 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 8/1/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/1/2022 | Approved | ARAM AVEDISIAN |
| Shower Pan | 8/1/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 8/5/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 8/5/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 8/10/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/10/2022 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 8/29/2022 | Approved | ARAM AVEDISIAN |
| Final | 8/29/2022 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 8/29/2022 | Approved | ARAM AVEDISIAN |
| Final | 9/13/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 12/5/2022 | OK to Issue CofO | ARAM AVEDISIAN |