15636 W TUBA ST 91343
Certificate Information: 15636 W TUBA ST 91343
- Application / Permit
- 21014-20000-04814
- Plan Check / Job No.
- B21VN12939
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION ( 20' X 17'-11" ) FOR NEW BEDROOM AND BATHROOM. ADDITION ( 17'-10" X 5' ) FOR LIVING ROOM EXPANSION. INTERIOR REMODEL AT KITCHEN AND BATHROOMS. WORK PER ENGINEER.
- Permit Issued
- Issued on 10/22/2021
- Issuing Office
- Current Status
- CofO Issued on 2/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2021 | ROSENDO MEDINA |
| Corrections Issued | 9/25/2021 | ROSENDO MEDINA |
| Plan Check Approved | 10/21/2021 | ROSENDO MEDINA |
| Issued | 10/22/2021 | APPLICANT |
| Building Plans Picked Up | 10/22/2021 | APPLICANT |
| CofO in Progress | 1/9/2023 | CHRISTOPHER DELLEFIELD |
| CofO in Progress | 1/13/2023 | JAVIER RAMOS JR |
| Permit Finaled | 2/4/2023 | MICHAEL SMITH |
| CofO Issued | 2/4/2023 | MICHAEL SMITH |
| Permit Finaled | 2/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/6/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/7/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lao,, Arturo Begino; Lic. No.: C56687 | 16348 MIDWOOD DR GRANADA HILLS, CA 91344 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/8/2021 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 11/8/2021 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 11/8/2021 | Partial Inspection | MICHEL ABAJAN |
| Green Building Rough | 11/8/2021 | Partial Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 11/8/2021 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 11/8/2021 | Partial Inspection | MICHEL ABAJAN |
| Pre-Inspection | 11/8/2021 | Partial Inspection | MICHEL ABAJAN |
| Sewer | 11/8/2021 | Partial Inspection | MICHEL ABAJAN |
| Wood Frame | 11/8/2021 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/18/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 11/18/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/18/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 11/18/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 11/18/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/18/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Sewer | 11/18/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 11/18/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/3/2021 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 12/3/2021 | Not Ready for Inspection | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 12/3/2021 | Conditional Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 12/3/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 12/3/2021 | Not Ready for Inspection | MARK JOHNSON |
| MERV13>=Rough | 12/3/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 12/3/2021 | Not Ready for Inspection | MARK JOHNSON |
| Reinforced Concrete Frame | 12/3/2021 | Not Ready for Inspection | MARK JOHNSON |
| Wood Frame | 12/3/2021 | Not Ready for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 12/23/2021 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 12/23/2021 | Not Ready for Inspection | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 12/23/2021 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2021 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Rough | 12/23/2021 | Not Ready for Inspection | RAUL OLAGI |
| MERV13>=Rough | 12/23/2021 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 12/23/2021 | Not Ready for Inspection | RAUL OLAGI |
| Piling/Pier/Caisson | 12/23/2021 | Not Ready for Inspection | RAUL OLAGI |
| Sewer | 12/23/2021 | Not Ready for Inspection | RAUL OLAGI |
| Wood Frame | 12/23/2021 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 12/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 12/30/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 12/30/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 12/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Sewer | 12/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 12/30/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 1/20/2022 | Partial Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 1/25/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 1/25/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 1/25/2022 | Partial Approval | JENNIFER RABUCHIN |
| MERV13>=Rough | 1/25/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 1/25/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/14/2022 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 2/14/2022 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 2/14/2022 | Not Ready for Inspection | RAUL OLAGI |
| MERV13>=Rough | 2/14/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 2/14/2022 | Not Ready for Inspection | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 2/14/2022 | Not Ready for Inspection | RAUL OLAGI |
| Wood Frame | 2/14/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 2/22/2022 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/12/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/12/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 4/12/2022 | Corrections Issued | JAVIER RAMOS JR |
| MERV13>=Rough | 4/12/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/12/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/20/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 4/20/2022 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 4/20/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 4/20/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/5/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/5/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/5/2022 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 5/5/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 5/11/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 5/11/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 5/26/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/27/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/5/2022 | Approved | JAVIER RAMOS JR |
| Final | 11/15/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 11/15/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| MERV13>=Final | 11/15/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 11/15/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 12/14/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 12/14/2022 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 12/14/2022 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 12/14/2022 | Approved | JAVIER RAMOS JR |