11708 N WOODLEY AVE 91344

Certificate Information: 11708 N WOODLEY AVE 91344

Application / Permit
21014-20000-04805
Plan Check / Job No.
B21VN12901
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2-STORY ADDITION AND MAJOR REMODEL TO (E) 2-STORY SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 07/30/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 2/27/2023
Issuing Office
Current Status
Issued on 2/27/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/25/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 RAPHAEL ROSAS
Corrections Issued 10/12/2021 RAPHAEL ROSAS
Building Plans Picked Up 12/15/2021 APPLICANT
Quality Review Completed 11/9/2022 OMID HEDAYAT
Applicant returned to address corrections 11/9/2022 RAPHAEL ROSAS
Applicant returned to address corrections 1/30/2023 RAPHAEL ROSAS
Plan Check Approved 2/23/2023 RAPHAEL ROSAS
Issued 2/27/2023 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 10/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 10/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 10/15/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 10/15/2021 CARLOS AGUILERA
Sewer availability Cleared 10/18/2021 CARLOS AGUILERA
Watercourse Cleared 10/18/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/25/2021 CARLOS AGUILERA
Distance to fire station Cleared 12/12/2021 ROBERT DUFF
Hydrant and Access approval Cleared 12/12/2021 ROBERT DUFF
Low Impact Development Cleared 6/3/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 6/27/2022 CARLOS AGUILERA
GPI Written Notices Cleared 2/23/2023 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 2/23/2023 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/30/2023 Not Ready for Inspection MARK DOVICO
Pre-Inspection 4/4/2023 Approved PIERRE VEGA
Underground Mechanical 4/17/2023 Approved MARK DOVICO
Deputy Drilled-In Anchors 4/24/2023 Approved ARIS ALLAHVERDIAN
Footing/Foundation/Slab 4/24/2023 Not Ready for Inspection ARIS ALLAHVERDIAN
Excavation/Setback/Form/Re-Bar 5/9/2023 Approved ARIS ALLAHVERDIAN
BUILDING-Rough-Frame 5/16/2023 Corrections Issued ARIS ALLAHVERDIAN
ELECTRICAL-Rough 5/16/2023 Corrections Issued ARIS ALLAHVERDIAN
Footing/Foundation/Slab 5/16/2023 Corrections Issued ARIS ALLAHVERDIAN
Special/Order Compliance 5/16/2023 Corrections Issued ARIS ALLAHVERDIAN
Reinforced Concrete Frame 6/7/2023 Not Ready for Inspection ARIS ALLAHVERDIAN
Structural Steel Frame 6/7/2023 Not Ready for Inspection ARIS ALLAHVERDIAN
Special/Order Compliance 6/8/2023 Corrections Issued ARIS ALLAHVERDIAN
Structural Steel Frame 6/27/2023 Corrections Issued ARIS ALLAHVERDIAN
BUILDING-Rough-Frame 7/12/2023 Not Ready for Inspection MARIO CUEVAS
Green Building Rough 7/12/2023 Not Ready for Inspection MARIO CUEVAS
Verify Sprinkler Sign Off 7/12/2023 Not Ready for Inspection MARIO CUEVAS
BUILDING-Rough-Frame 7/14/2023 Not Ready for Inspection MARIO CUEVAS
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Not Ready for Inspection MARIO CUEVAS
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Approved MARIO CUEVAS
Deputy Wood Construction 8/15/2023 Approved MARIO CUEVAS
Deputy Wood Construction 8/17/2023 Approved MARIO CUEVAS
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Approved MARIO CUEVAS
HVAC-Rough 1/31/2024 Not Ready for Inspection GARY PARKER
Insulation 1/31/2024 Not Ready for Inspection GARY PARKER
Interior/Exterior Lathing 5/23/2024 Not Ready for Inspection ARA SINANIAN
BUILDING-Rough-Frame 6/5/2024 Not Ready for Inspection ARA SINANIAN
Deputy Wood Construction 6/5/2024 Corrections Issued ARA SINANIAN
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Not Ready for Inspection ARA SINANIAN
Green Building Rough 6/5/2024 Not Ready for Inspection ARA SINANIAN
Rough-Elec/Plmb/HVAC 6/5/2024 Not Ready for Inspection ARA SINANIAN
Verify Sprinkler Sign Off 6/5/2024 Not Ready for Inspection ARA SINANIAN
ELECTRICAL-Rough 7/2/2024 Corrections Issued ARA SINANIAN
PLUMBING-Rough 7/2/2024 Partial Approval ARA SINANIAN
BUILDING-Rough-Frame 7/16/2024 Corrections Issued PIERRE VEGA
ELECTRICAL-Rough 7/16/2024 Corrections Issued PIERRE VEGA
HVAC-Rough 7/16/2024 Approved PIERRE VEGA
PLUMBING-Rough 7/16/2024 Approved PIERRE VEGA
ELECTRICAL-Rough 10/16/2024 Not Ready for Inspection ARA SINANIAN
Light Gage Steel Frame 10/25/2024 Corrections Issued ARA SINANIAN
Sewer 7/22/2025 Approved ARA SINANIAN
Underground Mechanical 7/22/2025 Approved ARA SINANIAN
ELECTRICAL-Rough 7/31/2025 Not Ready for Inspection ARA SINANIAN
Footing/Foundation/Slab 10/29/2025 No Access for Inspection ARA SINANIAN
Excavation/Setback/Form/Re-Bar 12/1/2025 Corrections Issued MARK DOVICO
Footing/Foundation/Slab 12/1/2025 Corrections Issued MARK DOVICO
Wood Frame 12/1/2025 Corrections Issued MARK DOVICO