11164-11166 N TAMARACK AVE 91331
Certificate Information: 11164-11166 N TAMARACK AVE 91331
- Application / Permit
- 21014-20000-04798
- Plan Check / Job No.
- B21VN12877
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXPAND AND CONVERT EXISTING COVERED PATIO INTO JRADU PER STATE LAW GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 4/9/2022
- Issuing Office
- Current Status
- CofO Issued on 7/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | MICHAEL LOPEZ |
| Corrections Issued | 10/8/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 10/19/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/22/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 12/23/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 1/11/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 1/28/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/8/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 4/8/2022 | MICHAEL LOPEZ |
| Issued | 4/9/2022 | APPLICANT |
| CofO in Progress | 7/13/2023 | MICHEL ABAJAN |
| Permit Finaled | 7/18/2023 | MICHAEL SMITH |
| CofO Issued | 7/18/2023 | MICHAEL SMITH |
| Permit Finaled | 7/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/15/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/6/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/6/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/6/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/9/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/9/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/9/2022 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Rough | 6/9/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/9/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/23/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/23/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/23/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/23/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/23/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/1/2022 | Partial Approval | ROBERT GOLD |
| Drywall Nailing | 7/22/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/6/2023 | Approved | MICHEL ABAJAN |
| Final | 1/6/2023 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Final | 1/6/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 1/6/2023 | Approved | MICHEL ABAJAN |
| Final | 4/21/2023 | Corrections Issued | MICHEL ABAJAN |
| Final | 6/2/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 7/10/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 7/12/2023 | OK to Issue CofO | MICHEL ABAJAN |