17432-17434 W ROSCOE BLVD 91325
Certificate Information: 17432-17434 W ROSCOE BLVD 91325
- Application / Permit
- 21014-20000-04796
- Plan Check / Job No.
- B21VN12875
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan 21' x 64' IRREGULAR SIZE ADU ADDITION TO (E) 1 STORY SFD. PER ORDINANCE 186481
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- CofO Issued on 12/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2021 | HERNAN ARREOLA |
| Corrections Issued | 9/26/2021 | HERNAN ARREOLA |
| Plan Check Approved | 12/20/2021 | HERNAN ARREOLA |
| Issued | 12/22/2021 | APPLICANT |
| CofO in Progress | 11/28/2022 | RAUL OLAGI |
| Permit Finaled | 12/2/2022 | DANIEL ORRANTE |
| CofO Issued | 12/2/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/2/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/5/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 11/22/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 12/9/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boules,, George Helmy; Lic. No.: NA64144 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Rough | 6/24/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 6/27/2022 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 6/27/2022 | Corrections Issued | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Partial Approval | ALAN MORELOS |
| Gas Test | 6/28/2022 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 6/28/2022 | Approved | ALAN MORELOS |
| HVAC-Rough | 7/1/2022 | Corrections Issued | ALAN MORELOS |
| HVAC-Rough | 7/5/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 7/5/2022 | Partial Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 8/29/2022 | Approved | ALAN MORELOS |
| Shower Pan | 8/29/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 9/8/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 9/8/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 9/20/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 9/20/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 9/20/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/13/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 10/13/2022 | Approved | RAUL OLAGI |
| Final | 10/13/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 10/13/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 10/13/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 10/13/2022 | Approved | RAUL OLAGI |
| Final | 11/28/2022 | OK to Issue CofO | RAUL OLAGI |