2925 S BENTLEY AVE 90064

Certificate Information: 2925 S BENTLEY AVE 90064

Application / Permit
21014-20000-04783
Plan Check / Job No.
B21VN12852
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
27'-7" X 20' IRREGULAR ADDITION TO (E) SFD FOR NEW BEDROOM, BATHROOM, WALK IN CLOSET. WORK PER DESIGN.
Permit Issued
Issued on 1/25/2022
Issuing Office
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2021 APPLICANT
Assigned to Plan Check Engineer 9/27/2021 ROSENDO MEDINA
Corrections Issued 9/27/2021 ROSENDO MEDINA
Applicant returned to address corrections 1/21/2022 ROSENDO MEDINA
Plan Check Approved 1/24/2022 ROSENDO MEDINA
Issued 1/25/2022 APPLICANT
Building Plans Picked Up 1/26/2022 APPLICANT
CofO in Progress 6/21/2025 MICHAEL PELHAM
Permit Finaled 6/23/2025 RICHARD STEINBACH
CofO Issued 6/23/2025 RICHARD STEINBACH
Permit Finaled 6/23/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 9/30/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 10/5/2021 DINAH GARIN
Grading Pre-Inspection Cleared 10/5/2021 BRIAN MILLER
Low Impact Development Cleared 1/7/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 1/7/2022 DINAH GARIN

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Butel Construction Inc; Lic. No.: 852273-B 257 SOUTH CITRUS AVE      LOS ANGELES, CA 90036

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 3/31/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 4/29/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 5/13/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 5/13/2022 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Approved JOHNNY MIRANDA
Green Building Rough 5/13/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 5/13/2022 Approved JOHNNY MIRANDA
MERV13>=Rough 5/13/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 5/13/2022 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 5/20/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 5/20/2022 Approved JOHNNY MIRANDA
Green Building Rough 5/20/2022 Approved JOHNNY MIRANDA
Insulation 5/20/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/20/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 5/20/2022 Approved JOHNNY MIRANDA
Shower Pan 5/20/2022 Approved JOHNNY MIRANDA
Drywall Nailing 5/25/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/25/2022 Approved JOHNNY MIRANDA
Final 8/31/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 8/31/2022 Approved JOHNNY MIRANDA
MERV13>=Final 8/31/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 8/31/2022 Approved JOHNNY MIRANDA
Final 6/21/2025 OK to Issue CofO MICHAEL PELHAM