10685 N KEWEN AVE 91331

Certificate Information: 10685 N KEWEN AVE 91331

Application / Permit
21014-20000-04771
Plan Check / Job No.
B21VN12820
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 15' X 20' TO (E) DETACHED 2-CAR GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/6/2022
Issuing Office
Current Status
CofO Issued on 9/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 GURUNATH NESARAJAH
Corrections Issued 9/25/2021 GURUNATH NESARAJAH
Plan Check Approved 2/4/2022 GURUNATH NESARAJAH
Issued 2/6/2022 APPLICANT
Building Plans Picked Up 2/9/2022 APPLICANT
CofO in Progress 9/2/2022 MICHEL ABAJAN
CofO Issued 9/7/2022 MICHAEL SMITH
Permit Finaled 9/7/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/13/2021 GABRIEL ROBLES
Address approval Cleared 10/20/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/21/2021 GABRIEL ROBLES
Sewer availability Cleared 10/21/2021 GABRIEL ROBLES
Construction near power lines Cleared 1/22/2022 RIDWAN HARDY
Clean Up Green Up Cleared 1/27/2022 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/12/2022 Partial Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 5/18/2022 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 5/27/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 5/27/2022 Corrections Issued JENNIFER RABUCHIN
METHANE-Barrier 5/27/2022 Approved JENNIFER RABUCHIN
METHANE-Subgrade 5/27/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/27/2022 Corrections Issued JENNIFER RABUCHIN
Sewer 5/27/2022 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 5/27/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 6/1/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/1/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/10/2022 Partial Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 6/10/2022 Approved JENNIFER RABUCHIN
Green Building Rough 6/10/2022 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 6/10/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/10/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/8/2022 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 7/13/2022 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 7/26/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 7/26/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 7/26/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 7/29/2022 Approved MICHEL ABAJAN
Green Building Rough 7/29/2022 Approved MICHEL ABAJAN
HVAC-Rough 7/29/2022 Approved MICHEL ABAJAN
Insulation 8/4/2022 Conditional Approval MICHEL ABAJAN
Drywall Nailing 8/10/2022 Approved MICHEL ABAJAN
Shower Pan 8/10/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/16/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 8/23/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 8/31/2022 Approved MICHEL ABAJAN
Final 8/31/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 8/31/2022 Approved MICHEL ABAJAN
HVAC-Final 8/31/2022 Approved MICHEL ABAJAN
PLUMBING-Final 8/31/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 8/31/2022 Approved MICHEL ABAJAN
Final 9/2/2022 OK to Issue CofO MICHEL ABAJAN