22924-22926 W OSTRONIC DR 91367
Certificate Information: 22924-22926 W OSTRONIC DR 91367
- Application / Permit
- 21014-20000-04762
- Plan Check / Job No.
- B21VN12801
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 17'-11" X 53'-8" ADDITION OF A NEW ACCESSORY DWELLING UNIT TO THE (E) SFD W/ ATTACHED GARAGE PER LAMC 12.22 A.33 (c) and (e).
- Permit Issued
- Issued on 7/5/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | PARISA ZAHABI |
| Corrections Issued | 9/23/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 1/7/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 1/27/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 2/18/2022 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 2/22/2022 | APPLICANT |
| Issued | 7/5/2022 | APPLICANT |
| CofO in Progress | 10/18/2024 | TROY SANDERS |
| Permit Finaled | 1/2/2025 | JOHN JANSON |
| CofO Issued | 1/2/2025 | JOHN JANSON |
| Permit Finaled | 1/2/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/28/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/30/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 10/29/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 11/8/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 1/13/2022 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/1/2022 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 8/2/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 8/2/2022 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 8/9/2022 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 8/9/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 8/9/2022 | Partial Approval | TROY SANDERS |
| Deputy Reinf. Concrete | 8/11/2022 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 9/22/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 10/18/2022 | Approved | TROY SANDERS |
| Green Building Rough | 10/18/2022 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 10/18/2022 | Approved | TROY SANDERS |
| MERV13>=Rough | 10/18/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 10/27/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 11/7/2022 | Approved | TROY SANDERS |
| Green Building Rough | 12/21/2022 | Approved | TROY SANDERS |
| Insulation | 12/21/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 12/21/2022 | Partial Approval | TROY SANDERS |
| Shower Pan | 12/21/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 12/28/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 1/24/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 10/26/2023 | Approved | TROY SANDERS |
| Service/Power Release | 10/26/2023 | Approved | TROY SANDERS |
| Final | 10/8/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 10/8/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| MERV13>=Final | 10/8/2024 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2024 | SGSOV Not Ready | GEVORK IPCHYAN |
| Smoke Detectors | 10/8/2024 | Approved | GEVORK IPCHYAN |
| Final | 10/17/2024 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 10/17/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Approved | TROY SANDERS |