22924-22926 W OSTRONIC DR 91367

Certificate Information: 22924-22926 W OSTRONIC DR 91367

Application / Permit
21014-20000-04762
Plan Check / Job No.
B21VN12801
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
17'-11" X 53'-8" ADDITION OF A NEW ACCESSORY DWELLING UNIT TO THE (E) SFD W/ ATTACHED GARAGE PER LAMC 12.22 A.33 (c) and (e).
Permit Issued
Issued on 7/5/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 PARISA ZAHABI
Corrections Issued 9/23/2021 PARISA ZAHABI
Applicant returned to address corrections 1/7/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 1/27/2022 MOHAMMAD ESMAILI
Plan Check Approved 2/18/2022 MOHAMMAD ESMAILI
Building Plans Picked Up 2/22/2022 APPLICANT
Issued 7/5/2022 APPLICANT
CofO in Progress 10/18/2024 TROY SANDERS
Permit Finaled 1/2/2025 JOHN JANSON
CofO Issued 1/2/2025 JOHN JANSON
Permit Finaled 1/2/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/28/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/30/2021 CARLOS AGUILERA
Sewer availability Cleared 9/30/2021 CARLOS AGUILERA
Low Impact Development Cleared 10/29/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 11/8/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 1/13/2022 VASIL MIHALEV

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/1/2022 Partial Approval TROY SANDERS
Footing/Foundation/Slab 8/2/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 8/2/2022 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 8/9/2022 Partial Approval TROY SANDERS
Footing/Foundation/Slab 8/9/2022 Approved TROY SANDERS
PLUMBING-Rough 8/9/2022 Partial Approval TROY SANDERS
Deputy Reinf. Concrete 8/11/2022 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/22/2022 Partial Approval TROY SANDERS
Underground Mechanical 9/22/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 10/18/2022 Approved TROY SANDERS
Green Building Rough 10/18/2022 Not Ready for Inspection TROY SANDERS
HVAC-Rough 10/18/2022 Approved TROY SANDERS
MERV13>=Rough 10/18/2022 Approved TROY SANDERS
PLUMBING-Rough 10/27/2022 Approved TROY SANDERS
ELECTRICAL-Rough 11/7/2022 Approved TROY SANDERS
Green Building Rough 12/21/2022 Approved TROY SANDERS
Insulation 12/21/2022 Approved TROY SANDERS
Interior/Exterior Lathing 12/21/2022 Partial Approval TROY SANDERS
Shower Pan 12/21/2022 Approved TROY SANDERS
Interior/Exterior Lathing 12/28/2022 Approved JESUS PINEDA
Drywall Nailing 1/24/2023 Approved JESUS PINEDA
ELECTRICAL-Final 10/26/2023 Approved TROY SANDERS
Service/Power Release 10/26/2023 Approved TROY SANDERS
Final 10/8/2024 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 10/8/2024 Not Ready for Inspection GEVORK IPCHYAN
MERV13>=Final 10/8/2024 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Not Ready GEVORK IPCHYAN
Smoke Detectors 10/8/2024 Approved GEVORK IPCHYAN
Final 10/17/2024 OK to Issue CofO TROY SANDERS
Green Building Final 10/17/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 10/17/2024 SGSOV Approved TROY SANDERS