7947 N HAZELTINE AVE 91402

Certificate Information: 7947 N HAZELTINE AVE 91402

Application / Permit
21014-20000-04759
Plan Check / Job No.
B21VN12787
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) ADDITION TO (E) 1-CAR GARAGE AND CONVERT TO 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 10/13/2021
Issuing Office
Current Status
CofO Issued on 6/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 DANIEL YIP
Corrections Issued 9/24/2021 DANIEL YIP
Applicant returned to address corrections 9/30/2021 DANIEL YIP
Plan Check Approved 10/6/2021 DANIEL YIP
Issued 10/13/2021 APPLICANT
CofO in Progress 4/8/2022 GREGG CUMMINGS
Permit Finaled 6/16/2022 DANIEL ORRANTE
CofO Issued 6/16/2022 DANIEL ORRANTE
Permit Finaled 6/16/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/27/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/27/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/27/2021 LEE GUILBEAUX
Sewer availability Cleared 9/27/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/27/2021 LEE GUILBEAUX
Construction within easement Cleared 9/28/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/9/2021 Conditional Approval WILLIAM WREN
Footing/Foundation/Slab 11/16/2021 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 11/16/2021 Partial Approval GREGG CUMMINGS
Sewer 11/16/2021 Approved GREGG CUMMINGS
Footing/Foundation/Slab 11/22/2021 Approved DAVID MATSON
PLUMBING-Rough 11/22/2021 Partial Approval DAVID MATSON
Underground Mechanical 11/22/2021 Partial Approval DAVID MATSON
ELECTRICAL-Rough 1/11/2022 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 1/11/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 1/11/2022 Corrections Issued GREGG CUMMINGS
Shower Pan 1/11/2022 Not Ready for Inspection GREGG CUMMINGS
Wood Frame 1/11/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 1/14/2022 Approved GREGG CUMMINGS
HVAC-Rough 1/14/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 1/14/2022 Approved GREGG CUMMINGS
Shower Pan 1/14/2022 Not Ready for Inspection GREGG CUMMINGS
Wood Frame 1/14/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 1/18/2022 Approved GREGG CUMMINGS
Shower Pan 1/18/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 1/21/2022 Partial Approval GREGG CUMMINGS
Insulation 1/26/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 1/28/2022 Approved GREGG CUMMINGS
Drywall Nailing 2/1/2022 Approved WILLIAM WREN
Underground Mechanical 2/7/2022 Partial Approval GREGG CUMMINGS
Final 3/14/2022 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 3/14/2022 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 3/14/2022 Approved GREGG CUMMINGS
ELECTRICAL-Final 4/7/2022 Approved GREGG CUMMINGS
Final 4/7/2022 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 4/7/2022 Approved GREGG CUMMINGS
PLUMBING-Final 4/7/2022 Approved GREGG CUMMINGS