16854 W MOONCREST DR 91436

Certificate Information: 16854 W MOONCREST DR 91436

Application / Permit
21014-20000-04755
Plan Check / Job No.
B21VN12775
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF EXTERIOR CLOSETS AND REPLACE & ENLARGE EXTERIOR DOORS. WORK PER ENGINEER.
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2021 APPLICANT
Assigned to Plan Check Engineer 9/21/2021 TROY DEGUZMAN
Corrections Issued 9/22/2021 TROY DEGUZMAN
Applicant returned to address corrections 11/10/2021 TROY DEGUZMAN
Building Plans Picked Up 11/16/2021 APPLICANT
Plan Check Approved 12/1/2021 TROY DEGUZMAN
Issued 12/2/2021 APPLICANT
CofO in Progress 11/15/2022 VINCENT HANLEY
Permit Finaled 11/19/2022 MICHAEL SMITH
CofO Issued 11/19/2022 MICHAEL SMITH
Permit Finaled 11/19/2022 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/14/2021 TROY DEGUZMAN
Green Code Cleared 11/14/2021 TROY DEGUZMAN

Contact Information

Architect Takacs,, David Alexander; Lic. No.: C33737 824 S. LOS ANGELES STREET      LOS ANGELES, CA 90014
Contractor Harris-Anderson; Lic. No.: 857280-B 11150 SANTA MONICA BLVD   SUITE 600    LOS ANGELES, CA 90025
Engineer Resnick,, Bruce Daniel; Lic. No.: S3293 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/28/2021 Approved PETER FOLLING
Deputy Steel/Welding 2/2/2022 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Approved DAVID SANDOVAL
Green Building Rough 2/25/2022 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 4/7/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/7/2022 Approved VINCENT HANLEY
Green Building Rough 4/7/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/7/2022 Approved VINCENT HANLEY
PLUMBING-Rough 4/7/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 11/8/2022 Approved VINCENT HANLEY
Final 11/8/2022 Corrections Issued VINCENT HANLEY
Green Building Final 11/8/2022 Approved VINCENT HANLEY
HVAC-Final 11/8/2022 Approved VINCENT HANLEY
PLUMBING-Final 11/8/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 11/8/2022 Approved VINCENT HANLEY
Final 11/15/2022 OK to Issue CofO VINCENT HANLEY