8237 W GROVE ST 91040
Certificate Information: 8237 W GROVE ST 91040
- Application / Permit
- 21014-20000-04752
- Plan Check / Job No.
- B21VN12738
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION ( 20'-3" X 18'-10" ) TO (E) SFD FOR NEW KITCHEN AND DINING ROOM. WORK PER ENGINEER.
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- CofO Issued on 11/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2021 | ROSENDO MEDINA |
| Corrections Issued | 9/27/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 11/19/2021 | ROSENDO MEDINA |
| Plan Check Approved | 12/29/2021 | ROSENDO MEDINA |
| Building Plans Picked Up | 12/29/2021 | APPLICANT |
| Issued | 1/12/2022 | APPLICANT |
| CofO in Progress | 10/5/2023 | WILLIAM WREN |
| CofO Issued | 11/18/2023 | RUBEN SALAS |
| Permit Finaled | 11/18/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/15/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 10/25/2021 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/8/2022 | Partial Inspection | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 4/20/2022 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 4/22/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/9/2022 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 7/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 7/20/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/20/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 7/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/25/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 7/25/2022 | Approved | MATTHEW NELSON |
| Insulation | 7/25/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 7/25/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Drywall Nailing | 7/27/2022 | Approved | MATTHEW NELSON |
| Final | 10/24/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 10/24/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/24/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 10/24/2022 | Approved | MATTHEW NELSON |
| Final | 9/13/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 9/13/2023 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 9/13/2023 | SGSOV Approved | WILLIAM WREN |
| Final | 9/19/2023 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 9/19/2023 | Approved | WILLIAM WREN |