8237 W GROVE ST 91040

Certificate Information: 8237 W GROVE ST 91040

Application / Permit
21014-20000-04752
Plan Check / Job No.
B21VN12738
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION ( 20'-3" X 18'-10" ) TO (E) SFD FOR NEW KITCHEN AND DINING ROOM. WORK PER ENGINEER.
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 11/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2021 APPLICANT
Assigned to Plan Check Engineer 9/27/2021 ROSENDO MEDINA
Corrections Issued 9/27/2021 ROSENDO MEDINA
Applicant returned to address corrections 11/19/2021 ROSENDO MEDINA
Plan Check Approved 12/29/2021 ROSENDO MEDINA
Building Plans Picked Up 12/29/2021 APPLICANT
Issued 1/12/2022 APPLICANT
CofO in Progress 10/5/2023 WILLIAM WREN
CofO Issued 11/18/2023 RUBEN SALAS
Permit Finaled 11/18/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/15/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/18/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 10/25/2021 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/8/2022 Partial Inspection MATTHEW NELSON
Deputy Drilled-In Anchors 4/20/2022 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 4/22/2022 Approved MATTHEW NELSON
PLUMBING-Rough 5/9/2022 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 7/15/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Partial Approval CHRISTOPHER DELLEFIELD
HVAC-Rough 7/20/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 7/20/2022 Partial Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/20/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/20/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/25/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 Approved MATTHEW NELSON
Green Building Rough 7/25/2022 Approved MATTHEW NELSON
Insulation 7/25/2022 Approved MATTHEW NELSON
Wood Frame 7/25/2022 Not Ready for Inspection MATTHEW NELSON
Drywall Nailing 7/27/2022 Approved MATTHEW NELSON
Final 10/24/2022 Corrections Issued MATTHEW NELSON
Green Building Final 10/24/2022 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 10/24/2022 Approved MATTHEW NELSON
Final 9/13/2023 Corrections Issued WILLIAM WREN
Green Building Final 9/13/2023 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 9/13/2023 SGSOV Approved WILLIAM WREN
Final 9/19/2023 OK to Issue CofO WILLIAM WREN
Green Building Final 9/19/2023 Approved WILLIAM WREN