361 S BUNDY DR 90049

Certificate Information: 361 S BUNDY DR 90049

Application / Permit
21014-20000-04748
Plan Check / Job No.
B21VN12730
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO CONSIST OF DEMOLISHING THE DWELLING MINUS THE (E) NORTHERLY WALL AND REBUILDING AN IRREGULAR 39'4" x 50'6" SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND AN ATTACHED IRREGULAR 12.25' x 36.67' TRELLIS. NFPA-13D REQUIRED THROUGHOUT.
Permit Issued
Issued on 3/23/2022
Issuing Office
Current Status
CofO Issued on 8/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 LUIS RINCON
Corrections Issued 10/2/2021 LUIS RINCON
Quality Review Completed 10/8/2021 OMID HEDAYAT
Applicant returned to address corrections 3/9/2022 LUIS RINCON
Plan Check Approved 3/15/2022 LUIS RINCON
Building Plans Picked Up 3/16/2022 APPLICANT
Issued 3/23/2022 APPLICANT
CofO in Progress 7/28/2023 OGANES TARAKHCHYAN
Permit Finaled 8/2/2023 DANIEL ORRANTE
CofO Issued 8/2/2023 DANIEL ORRANTE
Permit Finaled 8/2/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/27/2021 DENNIS BRAGIN
Sewer availability Cleared 10/27/2021 DENNIS BRAGIN
Sewer availability Cleared 10/27/2021 DENNIS BRAGIN
Low Impact Development Cleared 1/20/2022 TA ANH
Roof/Waste drainage to street Cleared 1/20/2022 DENNIS BRAGIN
Grading Pre-Inspection Cleared 2/4/2022 LUIS RINCON

Contact Information

Contractor Lush Remodeling Corporation; Lic. No.: 1073605-B 555 SOUTH BARRINGTON AVE #226      LOS ANGELES, CA 90049
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/26/2022 Partial Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 5/2/2022 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/6/2022 Corrections Issued JOHN KIDWELL
Deputy Reinf. Concrete 5/11/2022 Partial Approval JOHN KIDWELL
Deputy Steel/Welding 5/16/2022 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 5/24/2022 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Corrections Issued OGANES TARAKHCHYAN
Deputy Wood Construction 5/27/2022 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 7/7/2022 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 7/7/2022 Partial Approval MICHAEL PELHAM
Verify Sprinkler Sign Off 7/7/2022 Approved MICHAEL PELHAM
Deputy Wood Construction 7/11/2022 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 7/12/2022 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 7/13/2022 Partial Approval JOHN KIDWELL
Sewer 7/13/2022 Approved JOHN KIDWELL
Underground Mechanical 7/13/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Partial Approval JOHN KIDWELL
PLUMBING-Rough 7/15/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 7/18/2022 Corrections Issued OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/18/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 7/19/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 7/19/2022 Corrections Issued KEVIN SARGSYAN
Wood Frame 7/19/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 7/22/2022 Approved KEVIN SARGSYAN
HVAC-Rough 7/22/2022 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 7/26/2022 Corrections Issued CARLOS MATAMOROS
Green Building Rough 7/26/2022 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 7/28/2022 Approved CARLOS MATAMOROS
Green Building Rough 7/28/2022 Approved CARLOS MATAMOROS
Insulation 8/4/2022 Approved KEVIN SARGSYAN
Shower Pan 8/4/2022 Approved KEVIN SARGSYAN
Drywall Nailing 8/9/2022 Not Ready for Inspection JUAN VALENZUELA
Interior/Exterior Lathing 8/9/2022 Not Ready for Inspection JUAN VALENZUELA
Drywall Nailing 8/11/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 8/11/2022 Approved STEPHANIE SWANSON
Gas Test 12/12/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 12/27/2022 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 12/27/2022 Not Ready for Inspection KEVIN SARGSYAN
Smoke Detectors 12/27/2022 Not Ready for Inspection KEVIN SARGSYAN
Drywall Nailing 1/25/2023 Approved DAVID FEILER
ELECTRICAL-Final 1/25/2023 Corrections Issued CLAYTON GRAHAM
Final 1/25/2023 Corrections Issued CLAYTON GRAHAM
Footing/Foundation/Slab 1/25/2023 Not Ready for Inspection CLAYTON GRAHAM
Green Building Final 1/25/2023 Corrections Issued CLAYTON GRAHAM
HVAC-Final 1/25/2023 Corrections Issued CLAYTON GRAHAM
PLUMBING-Final 1/25/2023 Corrections Issued CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Not Ready CLAYTON GRAHAM
Smoke Detectors 1/25/2023 Approved CLAYTON GRAHAM
ELECTRICAL-Final 2/1/2023 Approved OGANES TARAKHCHYAN
HVAC-Final 2/1/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Final 2/1/2023 Partial Approval OGANES TARAKHCHYAN
Final 2/7/2023 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 2/7/2023 Approved OGANES TARAKHCHYAN
Green Building Final 2/7/2023 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/7/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Final 2/17/2023 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 2/17/2023 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/17/2023 SGSOV Approved OGANES TARAKHCHYAN
Final 2/28/2023 Corrections Issued OGANES TARAKHCHYAN
Special/Order Compliance 3/2/2023 Approved OGANES TARAKHCHYAN
Final 7/28/2023 OK to Issue CofO OGANES TARAKHCHYAN