610 1/2 W 107TH ST 90044

Certificate Information: 610 1/2 W 107TH ST 90044

Application / Permit
21014-20000-04742
Plan Check / Job No.
B21VN12716
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
3' X 24' ADDITION TO AND CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
Permit Issued
Issued on 10/20/2021
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 SERGIO MUNIZ
Corrections Issued 9/23/2021 SERGIO MUNIZ
Plan Check Approved 10/18/2021 SERGIO MUNIZ
Issued 10/20/2021 APPLICANT
Building Plans Picked Up 10/28/2021 APPLICANT
CofO in Progress 9/29/2022 ALIZAH MAYAGOITIA
Permit Finaled 10/15/2022 DEROLD HAUFF
CofO Issued 10/15/2022 DEROLD HAUFF
Permit Finaled 10/15/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/2/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 10/2/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 10/4/2021 RENZ SORIANO
Sewer availability Cleared 10/4/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/20/2022 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 2/28/2022 Partial Approval JOHN KLARIN
Sewer 2/28/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 3/9/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 4/11/2022 Corrections Issued EUGENE CASSIDY
Gas Test 4/11/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/14/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 4/14/2022 Approved JOHN KLARIN
Gas Test 4/14/2022 Approved JOHN KLARIN
Green Building Rough 4/14/2022 Approved JOHN KLARIN
Insulation 4/21/2022 Approved JOHN KLARIN
Sewer 4/21/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 6/2/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/2/2022 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 6/2/2022 Partial Approval ALIZAH MAYAGOITIA
Special/Order Compliance 6/28/2022 Corrections Issued JOHN KLARIN
Interior/Exterior Lathing 7/1/2022 Approved JOHN KLARIN
ELECTRICAL-Final 7/6/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 8/30/2022 Not Ready for Inspection EUGENE CASSIDY
Final 8/30/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 8/30/2022 Approved EUGENE CASSIDY
Green Building Final 8/30/2022 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 8/30/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 8/30/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 8/30/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 9/7/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 9/7/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 9/7/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 9/7/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 9/7/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 9/7/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 9/22/2022 Approved ALIZAH MAYAGOITIA
Final 9/22/2022 Conditional Approval ALIZAH MAYAGOITIA
Green Building Final 9/22/2022 Approved ALIZAH MAYAGOITIA
Final 9/28/2022 Conditional Approval ALIZAH MAYAGOITIA
Final 9/29/2022 OK to Issue CofO ALIZAH MAYAGOITIA