6028 N ETHEL AVE 91401
Certificate Information: 6028 N ETHEL AVE 91401
- Application / Permit
- 21014-20000-04716
- Plan Check / Job No.
- B21VN12645
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 25'11" X 11'5" ADDITION TO THE (E) SFD TO CREATE A NEW BEDROOM , NEW BATHROOM AND NEW POWER ROOM , NEW 12'5" X 8'10" ADDITION TO (E) SFD TO CREATE A NEW HOME OFFICE, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/23/2021
- Issuing Office
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2021 | RARES BODEA |
| Corrections Issued | 10/6/2021 | RARES BODEA |
| Plan Check Approved | 11/23/2021 | RARES BODEA |
| Issued | 11/23/2021 | APPLICANT |
| Building Plans Picked Up | 11/24/2021 | APPLICANT |
| CofO in Progress | 8/26/2022 | RAFAEL CORTES |
| CofO Issued | 9/3/2022 | MICHAEL SMITH |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/25/2021 | LEE GUILBEAUX |
| ZA Case | Cleared | 10/25/2021 | DANG NGUYEN |
| Roof/Waste drainage to street | Cleared | 11/23/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | H & O Unique Construction Inc; Lic. No.: 1016124-B | 16350 VENTURA BLVD #D106 ENCINO, CA 91436 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/15/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 2/16/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 2/24/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 3/1/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/1/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 3/9/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 3/9/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 3/14/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 3/14/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 3/21/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/21/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 3/30/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 3/30/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 3/30/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/30/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 3/30/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 4/4/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 4/4/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/4/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 4/4/2022 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 4/13/2022 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 4/13/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 6/29/2022 | Approved | RAFAEL CORTES |
| Final | 6/29/2022 | Corrections Issued | RAFAEL CORTES |
| Green Building Final | 6/29/2022 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 6/29/2022 | Approved | RAFAEL CORTES |
| Final | 8/25/2022 | OK to Issue CofO | RAFAEL CORTES |
| Green Building Final | 8/25/2022 | Approved | RAFAEL CORTES |