6028 N ETHEL AVE 91401

Certificate Information: 6028 N ETHEL AVE 91401

Application / Permit
21014-20000-04716
Plan Check / Job No.
B21VN12645
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 25'11" X 11'5" ADDITION TO THE (E) SFD TO CREATE A NEW BEDROOM , NEW BATHROOM AND NEW POWER ROOM , NEW 12'5" X 8'10" ADDITION TO (E) SFD TO CREATE A NEW HOME OFFICE, ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/23/2021
Issuing Office
Current Status
CofO Issued on 9/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2021 APPLICANT
Assigned to Plan Check Engineer 10/5/2021 RARES BODEA
Corrections Issued 10/6/2021 RARES BODEA
Plan Check Approved 11/23/2021 RARES BODEA
Issued 11/23/2021 APPLICANT
Building Plans Picked Up 11/24/2021 APPLICANT
CofO in Progress 8/26/2022 RAFAEL CORTES
CofO Issued 9/3/2022 MICHAEL SMITH
Permit Finaled 9/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/25/2021 LEE GUILBEAUX
Sewer availability Cleared 10/25/2021 LEE GUILBEAUX
ZA Case Cleared 10/25/2021 DANG NGUYEN
Roof/Waste drainage to street Cleared 11/23/2021 DAGOVERTO GUERRERO

Contact Information

Contractor H & O Unique Construction Inc; Lic. No.: 1016124-B 16350 VENTURA BLVD #D106      ENCINO, CA 91436
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/15/2022 Conditional Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 2/16/2022 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 2/24/2022 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 3/1/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 3/1/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/9/2022 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 3/9/2022 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Partial Approval CHRISTOPHE COCHRAN
Insulation 3/14/2022 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 3/14/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/21/2022 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 3/21/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/30/2022 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/30/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 3/30/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/30/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 3/30/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 4/4/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 4/4/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 4/4/2022 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 4/4/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 4/13/2022 Approved CHRISTOPHE COCHRAN
Insulation 4/13/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 6/29/2022 Approved RAFAEL CORTES
Final 6/29/2022 Corrections Issued RAFAEL CORTES
Green Building Final 6/29/2022 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 6/29/2022 SGSOV Approved RAFAEL CORTES
Smoke Detectors 6/29/2022 Approved RAFAEL CORTES
Final 8/25/2022 OK to Issue CofO RAFAEL CORTES
Green Building Final 8/25/2022 Approved RAFAEL CORTES