7838 N FERNCOLA AVE 91352

Certificate Information: 7838 N FERNCOLA AVE 91352

Application / Permit
21014-20000-04705
Plan Check / Job No.
B21VN12617
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF A BATHROOM TO THE (E) SFD.
Permit Issued
Issued on 10/3/2021
Issuing Office
Current Status
CofO Issued on 1/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2021 APPLICANT
Assigned to Plan Check Engineer 9/21/2021 JESSE ARELLANO
Corrections Issued 9/21/2021 JESSE ARELLANO
Applicant returned to address corrections 9/30/2021 JESSE ARELLANO
Issued 10/3/2021 APPLICANT
Building Plans Picked Up 10/7/2021 APPLICANT
CofO in Progress 12/8/2021 WILLIAM KUEHN
Permit Finaled 1/25/2022 MICHAEL SMITH
CofO Issued 1/25/2022 MICHAEL SMITH
Permit Finaled 1/25/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/22/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 9/22/2021 DAGOVERTO GUERRERO
Green Code Cleared 9/30/2021 JESSE ARELLANO

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/25/2021 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 11/1/2021 Partial Approval DAVID MATSON
Green Building Rough 11/1/2021 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 11/1/2021 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 11/8/2021 Approved WILLIAM KUEHN
ELECTRICAL-Rough 11/8/2021 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Approved WILLIAM KUEHN
Green Building Rough 11/8/2021 Not Ready for Inspection WILLIAM KUEHN
PLUMBING-Rough 11/8/2021 Approved WILLIAM KUEHN
Insulation 11/16/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 11/16/2021 Partial Inspection WILLIAM KUEHN
Drywall Nailing 11/19/2021 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 12/7/2021 Approved WILLIAM KUEHN
ELECTRICAL-Final 12/7/2021 Approved WILLIAM KUEHN
Final 12/7/2021 OK to Issue CofO WILLIAM KUEHN
Green Building Final 12/7/2021 Approved WILLIAM KUEHN
Green Building Rough 12/7/2021 Approved WILLIAM KUEHN
PLUMBING-Final 12/7/2021 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 12/7/2021 SGSOV Approved WILLIAM KUEHN