12236 N CATENIA DR 91344

Certificate Information: 12236 N CATENIA DR 91344

Application / Permit
21014-20000-04692
Plan Check / Job No.
B21VN12568
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND COVERED PATIOS. PORTION OF EXTERIOR WALL AND FOOTING TO REMAIN ON THE NORTH-WEST PART OF THE BUILDING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/26/2022
Issuing Office
Current Status
CofO Issued on 9/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 COLIN LOREDO
Corrections Issued 10/19/2021 COLIN LOREDO
Quality Review Completed 10/27/2021 OMID HEDAYAT
Building Plans Picked Up 10/29/2021 APPLICANT
Plan Check Approved 4/5/2022 COLIN LOREDO
Issued 4/26/2022 APPLICANT
CofO in Progress 8/21/2023 JAVIER RAMOS JR
Permit Finaled 9/22/2023 RUBEN SALAS
CofO Issued 9/22/2023 RUBEN SALAS
Permit Finaled 9/22/2023 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/22/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/22/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/22/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/22/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 12/22/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/27/2021 CARLOS AGUILERA
Sewer availability Cleared 12/27/2021 CARLOS AGUILERA
Low Impact Development Cleared 3/7/2022 MARTIN FRAGOSO
GPI Written Notices Cleared 4/5/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 4/5/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 4/15/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/21/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 6/30/2022 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/26/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 9/26/2022 Corrections Issued JAVIER RAMOS JR
Deputy Drilled-In Anchors 9/28/2022 Conditional Approval DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 10/28/2022 Partial Approval JAVIER RAMOS JR
Underground Mechanical 10/28/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 1/12/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 1/12/2023 Approved JAVIER RAMOS JR
Green Building Rough 1/12/2023 Approved JAVIER RAMOS JR
HVAC-Rough 1/12/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 1/12/2023 Approved JAVIER RAMOS JR
Sewer 1/12/2023 Approved JAVIER RAMOS JR
Shower Pan 1/12/2023 Partial Approval JAVIER RAMOS JR
Verify Sprinkler Sign Off 1/12/2023 Approved JAVIER RAMOS JR
Insulation 2/7/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 2/17/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 2/17/2023 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 3/15/2023 Approved JAVIER RAMOS JR
Pre-Inspection 3/15/2023 Approved JAVIER RAMOS JR
Shower Pan 3/15/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/16/2023 Partial Approval JAVIER RAMOS JR
Final 8/14/2023 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 8/14/2023 Approved JAVIER RAMOS JR
Green Building Final 8/14/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/14/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 8/14/2023 Approved JAVIER RAMOS JR
Final 8/18/2023 OK to Issue CofO JAVIER RAMOS JR