4617 N CARTWRIGHT AVE 91602

Certificate Information: 4617 N CARTWRIGHT AVE 91602

Application / Permit
21014-20000-04684
Plan Check / Job No.
B21VN12539
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 16-11" X 18'-6" TO (E) 19'-6" X 20' GARAGE AND CONVERT ENTIRE STRUCTURE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER WFPP
Permit Issued
Issued on 7/9/2022
Issuing Office
Current Status
CofO Issued on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2021 APPLICANT
Assigned to Plan Check Engineer 9/17/2021 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 9/19/2021 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 9/30/2021 APPLICANT
Applicant returned to address corrections 11/15/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 3/16/2022 SEWADA ZADOORAN MILAGARDI
Issued 7/9/2022 APPLICANT
CofO in Progress 12/18/2024 CHRISTOPHER ROJAS
Permit Finaled 12/24/2024 RUBEN SALAS
CofO Issued 12/24/2024 RUBEN SALAS
Permit Finaled 12/24/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/13/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 10/13/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/15/2021 CARLOS AGUILERA
Sewer availability Cleared 10/15/2021 CARLOS AGUILERA
Construction near power lines Cleared 3/16/2022 RIDWAN HARDY
Construction within easement Cleared 3/16/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/9/2024 Corrections Issued KIRK SANDERS
Underground Mechanical 4/9/2024 Partial Approval KIRK SANDERS
Deputy Drilled-In Anchors 4/25/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/12/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 7/17/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 7/17/2024 Approved CHRISTOPHER ROJAS
MERV13>=Rough 7/17/2024 Approved CHRISTOPHER ROJAS
Sewer 7/17/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 8/22/2024 Approved CHRISTOPHER ROJAS
Insulation 8/26/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/29/2024 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 9/3/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 9/3/2024 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 9/12/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 9/12/2024 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 9/12/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 10/11/2024 Corrections Issued CHRISTOPHER ROJAS
Gas Test 10/16/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 10/16/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 11/18/2024 Approved JUAN VALENZUELA
ELECTRICAL-Final 11/18/2024 Approved JUAN VALENZUELA
Final 11/18/2024 Corrections Issued JUAN VALENZUELA
Green Building Final 11/18/2024 Approved JUAN VALENZUELA
HVAC-Final 11/18/2024 Corrections Issued JUAN VALENZUELA
MERV13>=Final 11/18/2024 Conditional Approval JUAN VALENZUELA
PLUMBING-Final 11/18/2024 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 11/18/2024 Approved JUAN VALENZUELA
Final 12/12/2024 OK to Issue CofO CHRISTOPHER ROJAS
MERV13>=Final 12/12/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/12/2024 SGSOV Approved CHRISTOPHER ROJAS