2831 N GRIFFIN AVE 90031

Certificate Information: 2831 N GRIFFIN AVE 90031

Application / Permit
21014-20000-04683
Plan Check / Job No.
B21VN12536
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 1ST AND 2ND FLOOR 22'3" X 25'9" IRREGULAR SHAPED TO AND CONVERT (E) 37'9-1/2" X 18'8-1/2" DETACHED (2) TWO CAR GARAGES INTO ACCESORY DWELLING UNIT AS PER LAMC 12.22.A.33(C) AND (E) WITH 3'8" X 7'6" STORAGE ROOM WITH EXTERIOR ACCESS, ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/6/2023
Issuing Office
Current Status
CofO Issued on 6/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 RARES BODEA
Corrections Issued 10/7/2021 RARES BODEA
Quality Review Completed 10/8/2021 STEVEN KIM
Building Plans Picked Up 10/19/2021 APPLICANT
Applicant returned to address corrections 8/31/2022 RARES BODEA
Applicant returned to address corrections 2/7/2023 RARES BODEA
Plan Check Approved 2/7/2023 RARES BODEA
Issued 4/6/2023 APPLICANT
CofO in Progress 5/20/2024 JACOB SEGURA
Permit Finaled 6/5/2024 DANIEL SANCHEZ
CofO Issued 6/5/2024 DANIEL SANCHEZ
Permit Finaled 6/5/2024 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 1/11/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 1/12/2022 ABEL CASILLAS
Roof/Waste drainage to street Cleared 1/12/2022 ABEL CASILLAS
Sewer availability Cleared 1/12/2022 ABEL CASILLAS
ZA Case Cleared 1/13/2022 DALIA MOKAYED
Construction near power lines Cleared 3/4/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 4/1/2022 DWAYNE LAURENT
HPOZ Cleared 1/24/2023 DAMIAN GATTO
ZI Cleared 1/24/2023 DAMIAN GATTO

Contact Information

Contractor Owner-Builder       ,
Engineer Barragan,, Pedro; Lic. No.: C90531 329 N HUBBARD AVE      SAN FERNANDO, CA 91340

Inspector Information

THOMAS WILLIS, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY CHRISTIAN, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
FERMIN RUBIO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JACOB SEGURA, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
CLAUDIO MORENO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
MARK RUDE, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/12/2023 Not Ready for Inspection JAVIER RAMOS SR
Sewer 7/12/2023 Partial Approval JAVIER RAMOS SR
Footing/Foundation/Slab 7/24/2023 Approved JAVIER RAMOS SR
BUILDING-Rough-Frame 8/10/2023 Not Ready for Inspection JAVIER RAMOS SR
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Partial Approval JAVIER RAMOS SR
Green Building Rough 8/10/2023 Not Ready for Inspection JAVIER RAMOS SR
Wood Frame 8/10/2023 Partial Approval JAVIER RAMOS SR
Wood Frame 9/21/2023 Partial Inspection LONG LEE
BUILDING-Rough-Frame 10/2/2023 Corrections Issued JACOB SEGURA
Green Building Rough 10/2/2023 Not Ready for Inspection JACOB SEGURA
Rough-Elec/Plmb/HVAC 10/2/2023 Corrections Issued JACOB SEGURA
BUILDING-Rough-Frame 10/16/2023 Partial Approval JACOB SEGURA
Green Building Rough 10/16/2023 Partial Approval JACOB SEGURA
Rough-Elec/Plmb/HVAC 10/16/2023 Partial Approval JACOB SEGURA
Interior/Exterior Lathing 10/23/2023 Not Ready for Inspection JAVIER RAMOS SR
BUILDING-Rough-Frame 10/24/2023 Corrections Issued JACOB SEGURA
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Approved JACOB SEGURA
Shower Pan 10/24/2023 Approved JACOB SEGURA
Special/Order Compliance 10/24/2023 Not Ready for Inspection JACOB SEGURA
Wood Frame 10/24/2023 Corrections Issued JACOB SEGURA
Insulation 11/3/2023 Approved LONG LEE
Drywall Nailing 11/13/2023 Conditional Approval JACOB SEGURA
Interior/Exterior Lathing 11/14/2023 Approved JACOB SEGURA
Interior/Exterior Lathing 11/20/2023 Approved JAVIER RAMOS SR
Sewer 12/4/2023 Conditional Approval JACOB SEGURA
Sewer 2/21/2024 Partial Approval JACOB SEGURA
BUILDING-Rough-Frame 2/26/2024 Approved JACOB SEGURA
Drywall Nailing 2/26/2024 Approved JACOB SEGURA
Final 2/26/2024 Not Ready for Inspection JACOB SEGURA
Green Building Final 2/26/2024 Approved JACOB SEGURA
Green Building Rough 2/26/2024 Approved JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Not Required JACOB SEGURA
Sewer 2/26/2024 Approved JACOB SEGURA
Smoke Detectors 2/26/2024 Approved JACOB SEGURA
Final 5/7/2024 Conditional Approval JACOB SEGURA
Final 5/17/2024 OK to Issue CofO JACOB SEGURA