131 N HOBART BLVD 90004

Certificate Information: 131 N HOBART BLVD 90004

Application / Permit
21014-20000-04680
Plan Check / Job No.
B21VN12527
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) REC. ROOM TO ACCESSORY DWELLING UNIT WITH 2ND STORY ADDITION PER LAMC 12.22A.33(c)-(d) WITH (E) ATTACHED GARAGE TO REMAIN. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/24/2022
Issuing Office
Current Status
CofO Issued on 6/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 COLIN LOREDO
Corrections Issued 10/19/2021 COLIN LOREDO
Quality Review Completed 11/1/2021 OMID HEDAYAT
Building Plans Picked Up 11/15/2021 APPLICANT
Applicant returned to address corrections 1/26/2022 COLIN LOREDO
Applicant returned to address corrections 4/11/2022 COLIN LOREDO
Applicant returned to address corrections 5/5/2022 COLIN LOREDO
Plan Check Approved 6/17/2022 COLIN LOREDO
Issued 6/24/2022 APPLICANT
CofO in Progress 6/5/2023 JEFFREY MEAD
No Progress 6/6/2023 SCOTT FINNILA
CofO in Progress 6/6/2023 SCOTT FINNILA
CofO in Progress 6/7/2023 JEFFREY MEAD
Permit Finaled 6/15/2023 DEROLD HAUFF
CofO Issued 6/15/2023 DEROLD HAUFF
Permit Finaled 6/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/10/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/3/2022 CINDY QI
Sewer availability Cleared 1/3/2022 CINDY QI
Low Impact Development Cleared 2/10/2022 LONDY ALVARADO
Construction near power lines Cleared 3/12/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 4/29/2022 CHRISTOPHER ROCHA

Contact Information

Contractor L J Prime Builders Inc; Lic. No.: 1061041-B 15158 RAYEN ST      NORTH HILLS, CA 91343
Engineer Tagudar,, Fred; Lic. No.: C33612 255 W 5TH ST APT 706      SAN PEDRO, CA 90731

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/18/2022 Approved JEFFREY MEAD
Deputy Drilled-In Anchors 8/1/2022 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 9/16/2022 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 9/16/2022 Corrections Issued JEFFREY MEAD
Green Building Rough 9/16/2022 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 9/19/2022 Partial Approval JEFFREY MEAD
Green Building Rough 9/19/2022 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 9/23/2022 Partial Approval JEFFREY MEAD
ELECTRICAL-Rough 9/23/2022 Approved JEFFREY MEAD
Green Building Rough 9/23/2022 Not Ready for Inspection JEFFREY MEAD
HVAC-Rough 9/23/2022 Approved JEFFREY MEAD
PLUMBING-Rough 9/23/2022 Not Ready for Inspection JEFFREY MEAD
PLUMBING-Rough 10/12/2022 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Approved JEFFREY MEAD
PLUMBING-Rough 10/14/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 10/26/2022 Approved JEFFREY MEAD
Insulation 11/1/2022 Approved JEFFREY MEAD
Drywall Nailing 11/8/2022 Approved JEFFREY MEAD
Green Building Rough 11/8/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 3/9/2023 Approved JEFFREY MEAD
Final 3/9/2023 Corrections Issued JEFFREY MEAD
Green Building Final 3/9/2023 Partial Approval JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 3/9/2023 SGSOV Approved JEFFREY MEAD
Smoke Detectors 3/9/2023 Approved JEFFREY MEAD
ELECTRICAL-Final 6/5/2023 Approved JEFFREY MEAD
Final 6/5/2023 Not Ready for Inspection JEFFREY MEAD
Green Building Final 6/5/2023 Approved JEFFREY MEAD
HVAC-Final 6/5/2023 Approved JEFFREY MEAD
PLUMBING-Final 6/5/2023 Approved JEFFREY MEAD
Final 6/7/2023 OK to Issue CofO JEFFREY MEAD