14851-14853 W STRATHERN ST 91402
Certificate Information: 14851-14853 W STRATHERN ST 91402
- Application / Permit
- 21014-20000-04678
- Plan Check / Job No.
- B21VN12524
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ECPC: 600 SQ. FT. ADDITION OF AN ACCESSORY DWELLING UNIT TO THE (E) SFD, PER LAMC 12.22 A.33 (c) AND (e). ALL WORK PER WFPP. ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/14/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 9/18/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 11/30/2021 | LUISANGEL VALENZUELA |
| Plan Check Approved | 12/9/2021 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 12/10/2021 | APPLICANT |
| Issued | 12/14/2021 | APPLICANT |
| CofO in Progress | 5/31/2023 | MATTHEW NELSON |
| CofO Issued | 6/5/2023 | MICHAEL SMITH |
| Permit Finaled | 6/5/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/22/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/14/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 11/19/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/1/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/4/2022 | Partial Approval | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 2/7/2022 | Conditional Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 2/14/2022 | Approved | MATT KELLERMAN |
| Special/Order Compliance | 3/17/2022 | Corrections Issued | GREGG CUMMINGS |
| Wood Frame | 5/4/2022 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Rough | 5/9/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/13/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/17/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/17/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/19/2022 | Approved | WILLIAM WREN |
| Insulation | 5/19/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 5/19/2022 | Approved | WILLIAM WREN |
| Wood Frame | 5/19/2022 | Not Ready for Inspection | WILLIAM WREN |
| Insulation | 5/24/2022 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 5/31/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 5/31/2022 | Approved | WILLIAM WREN |
| Underground Mechanical | 5/31/2022 | Not Ready for Inspection | WILLIAM WREN |
| Insulation | 6/6/2022 | Approved | DAVID MATSON |
| Drywall Nailing | 6/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 6/9/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 6/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 6/14/2022 | Corrections Issued | WILLIAM WREN |
| Shower Pan | 6/17/2022 | Approved | WILLIAM WREN |
| Final | 7/7/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/7/2022 | Approved | GREGG CUMMINGS |
| Green Building Final | 7/7/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/7/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 7/7/2022 | Approved | GREGG CUMMINGS |
| Final | 8/4/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 2/27/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 3/6/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 3/6/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 3/6/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 3/6/2023 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 3/6/2023 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/11/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 4/11/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/11/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 5/30/2023 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 5/30/2023 | Approved | MATTHEW NELSON |