8125 N TILDEN AVE 91402

Certificate Information: 8125 N TILDEN AVE 91402

Application / Permit
21014-20000-04676
Plan Check / Job No.
B21VN12518
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD & EXPAND ( 18'-7"x 6'-0) BEDROOM TO THE (E) ONE STORY SINGLE FAMILY DWELLING AND RELOCATE THE (E) BATHROOM. WORK PER ENGINEER. "COMPLY WITH DEPARTMENT ORDER effective date 01/05/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 11/12/2021
Issuing Office
Current Status
Issued on 11/12/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/16/2021 APPLICANT
Assigned to Plan Check Engineer 9/17/2021 TROY DEGUZMAN
Corrections Issued 9/18/2021 TROY DEGUZMAN
Building Plans Picked Up 9/22/2021 APPLICANT
Applicant returned to address corrections 10/14/2021 TROY DEGUZMAN
Plan Check Approved 11/10/2021 TROY DEGUZMAN
Issued 11/12/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/19/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/19/2021 LEE GUILBEAUX
Sewer availability Cleared 10/19/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Sadjadi,, Abdulreza; Lic. No.: C51812 1223 WILSHIRE BLVD #169      SANTA MONICA, CA 90403

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2022 Corrections Issued MICKEY YAMASHITA
Pre-Inspection 2/3/2022 Corrections Issued MICKEY YAMASHITA
Deputy Drilled-In Anchors 4/7/2022 Approved THOMAS WOODS
BUILDING-Rough-Frame 5/11/2022 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 5/11/2022 Not Ready for Inspection MICKEY YAMASHITA
Footing/Foundation/Slab 5/11/2022 Corrections Issued MICKEY YAMASHITA
Green Building Rough 5/11/2022 Not Ready for Inspection MICKEY YAMASHITA
PLUMBING-Rough 5/11/2022 Not Ready for Inspection MICKEY YAMASHITA
BUILDING-Rough-Frame 6/22/2022 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 6/22/2022 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 6/28/2022 Not Ready for Inspection MICKEY YAMASHITA
Footing/Foundation/Slab 6/28/2022 Corrections Issued MICKEY YAMASHITA
Green Building Rough 6/28/2022 Not Ready for Inspection MICKEY YAMASHITA
BUILDING-Rough-Frame 6/30/2022 Not Ready for Inspection MICKEY YAMASHITA
ELECTRICAL-Rough 6/30/2022 Not Ready for Inspection MICKEY YAMASHITA
Footing/Foundation/Slab 6/30/2022 Corrections Issued MICKEY YAMASHITA
Green Building Rough 6/30/2022 Not Ready for Inspection MICKEY YAMASHITA
PLUMBING-Rough 6/30/2022 Not Ready for Inspection MICKEY YAMASHITA
ELECTRICAL-Rough 7/6/2022 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 7/6/2022 Approved MICKEY YAMASHITA
Green Building Rough 7/6/2022 Not Ready for Inspection MICKEY YAMASHITA
Interior/Exterior Lathing 7/6/2022 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 7/6/2022 Corrections Issued MICKEY YAMASHITA
Deputy Drilled-In Anchors 7/8/2022 Conditional Approval MICKEY YAMASHITA
BUILDING-Rough-Frame 7/12/2022 Not Ready for Inspection MICKEY YAMASHITA
ELECTRICAL-Rough 7/12/2022 Conditional Approval MICKEY YAMASHITA
Green Building Rough 7/12/2022 Not Ready for Inspection MICKEY YAMASHITA
PLUMBING-Rough 7/12/2022 Conditional Approval MICKEY YAMASHITA
BUILDING-Rough-Frame 7/21/2022 Approved THOMAS WOODS
ELECTRICAL-Rough 7/21/2022 Approved THOMAS WOODS
Green Building Rough 7/21/2022 Approved THOMAS WOODS
PLUMBING-Rough 7/21/2022 Approved THOMAS WOODS
Insulation 7/25/2022 Approved MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Approved THOMAS WOODS
Interior/Exterior Lathing 8/1/2022 Partial Approval THOMAS WOODS
Shower Pan 8/1/2022 Approved THOMAS WOODS
Drywall Nailing 8/8/2022 Approved THOMAS WOODS
ELECTRICAL-Final 9/26/2022 Approved THOMAS WOODS
Final 9/26/2022 Conditional Approval THOMAS WOODS
Green Building Final 9/26/2022 Approved THOMAS WOODS
HVAC-Final 9/26/2022 Approved THOMAS WOODS
Insulation 9/26/2022 Approved THOMAS WOODS
PLUMBING-Final 9/26/2022 Approved THOMAS WOODS
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Approved THOMAS WOODS
Smoke Detectors 9/26/2022 Approved THOMAS WOODS
Gas Test 4/27/2023 Not Ready for Inspection LUCIANO GAUNA