5249 N RANCHITO AVE 91401
Certificate Information: 5249 N RANCHITO AVE 91401
- Application / Permit
- 21014-20000-04664
- Plan Check / Job No.
- B21VN12489
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 28'-6" X 39-4 IRREGULAR SHAPED ADDITION & REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | MARVEL DELACRUZ |
| Corrections Issued | 11/2/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 11/9/2021 | STEVEN KIM |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| Applicant returned to address corrections | 2/11/2022 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 3/11/2022 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 4/28/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 5/2/2022 | RAPHAEL ROSAS |
| Issued | 5/12/2022 | APPLICANT |
| CofO in Progress | 2/24/2023 | RYAN SALAZAR |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
| CofO Issued | 4/18/2023 | MICHAEL SMITH |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/2/2022 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 4/15/2022 | CHRIS VONG |
| Green Code | Cleared | 4/28/2022 | MARVEL DELACRUZ |
| Roof/Waste drainage to street | Cleared | 4/28/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Milspec Builders Inc; Lic. No.: 1017487-B | 4996 ALTA ST SIMI VALLEY, CA 93063 |
| Engineer | Luisoni,, Antonio Stefano; Lic. No.: S1781 | 12757 DEON PLACE GRANADA HILLS, CA 91344 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/16/2022 | Approved | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 5/17/2022 | Conditional Approval | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 5/18/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Rough | 5/18/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 5/18/2022 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 8/1/2022 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 8/1/2022 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/8/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/8/2022 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 9/8/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/12/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 9/12/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/12/2022 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 9/12/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/15/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 9/15/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 9/15/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 9/15/2022 | Approved | RICHARD DOCKUS |
| Insulation | 9/16/2022 | Not Ready for Inspection | ALAN MORELOS |
| Insulation | 9/22/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 9/27/2022 | Approved | WILLIAM WREN |
| Shower Pan | 9/27/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/16/2022 | Partial Approval | RICHARD DOCKUS |
| Interior/Exterior Lathing | 11/23/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 1/24/2023 | Corrections Issued | RYAN SALAZAR |
| HVAC-Final | 1/24/2023 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Final | 1/27/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 1/27/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 1/27/2023 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Final | 1/27/2023 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Final | 1/27/2023 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/27/2023 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 1/27/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 2/24/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 2/24/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 2/24/2023 | Approved | RYAN SALAZAR |