12216 W JUNIETTE ST 90230

Certificate Information: 12216 W JUNIETTE ST 90230

Application / Permit
21014-20000-04642
Plan Check / Job No.
B21VN12436
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (35'-2 1/2"x 24'-8") IRR SHAPE AND CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 11/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2021 APPLICANT
Assigned to Plan Check Engineer 9/17/2021 TROY DEGUZMAN
Corrections Issued 9/18/2021 TROY DEGUZMAN
Building Plans Picked Up 9/22/2021 APPLICANT
Plan Check Approved 3/2/2022 TROY DEGUZMAN
Issued 3/2/2022 APPLICANT
CofO in Progress 11/4/2022 HERBERT GIRON
Permit Finaled 11/15/2022 DANIEL ORRANTE
CofO Issued 11/15/2022 DANIEL ORRANTE
Permit Finaled 11/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/14/2021 DINAH GARIN
Low Impact Development Cleared 1/25/2022 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 1/28/2022 DINAH GARIN
Sewer availability Cleared 1/28/2022 DINAH GARIN
Hydrant and Access approval Cleared 2/1/2022 OSCAR SALGADO JR
Roof/Waste drainage to street Cleared 2/4/2022 JOSE HERNANDEZ

Contact Information

Contractor Wetzel Homes Inc; Lic. No.: 1058085-B 3531 N GALVESTON AVE      SIMI VALLEY, CA 93063
Engineer Shakiban,, George; Lic. No.: C39908 23945 CALABASAS RD STE 101      CALABASAS, CA 91302

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/14/2022 Corrections Issued DAVID FEILER
METHANE-Subgrade 3/14/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 3/14/2022 Partial Approval DAVID FEILER
METHANE-Subgrade 3/16/2022 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/25/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 3/25/2022 Not Ready for Inspection BOBBY KEY
METHANE-Barrier 3/25/2022 Not Ready for Inspection BOBBY KEY
METHANE-Subgrade 3/25/2022 Not Ready for Inspection BOBBY KEY
Footing/Foundation/Slab 3/31/2022 Approved RICHARD STEINBACH
METHANE-Barrier 3/31/2022 Approved RICHARD STEINBACH
METHANE-Subgrade 3/31/2022 Approved RICHARD STEINBACH
Deputy Wood Construction 5/17/2022 Conditional Approval RICHARD STEINBACH
ELECTRICAL-Rough 6/8/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 6/8/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 6/8/2022 Conditional Approval STEPHANIE SWANSON
ELECTRICAL-Rough 7/6/2022 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Conditional Approval JESUS RODRIGUEZ
Green Building Rough 7/6/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 7/6/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 7/6/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 8/1/2022 Corrections Issued HERBERT GIRON
HVAC-Rough 8/1/2022 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 8/1/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 8/4/2022 Approved HERBERT GIRON
HVAC-Rough 8/4/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 8/4/2022 Approved HERBERT GIRON
Insulation 8/8/2022 Corrections Issued HERBERT GIRON
Insulation 8/9/2022 Conditional Approval HERBERT GIRON
Drywall Nailing 8/12/2022 Partial Approval HERBERT GIRON
Green Building Rough 8/12/2022 Not Ready for Inspection HERBERT GIRON
Green Building Rough 8/30/2022 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 8/30/2022 Approved HERBERT GIRON
Shower Pan 8/30/2022 Approved HERBERT GIRON
Gas Test 10/14/2022 Corrections Issued HERBERT GIRON
METHANE-Final 10/14/2022 Approved HERBERT GIRON
PLUMBING-Final 10/14/2022 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 10/14/2022 SGSOV Approved HERBERT GIRON
Gas Test 10/18/2022 Corrections Issued HERBERT GIRON
PLUMBING-Final 10/18/2022 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 10/28/2022 Approved HERBERT GIRON
Drywall Nailing 10/28/2022 Approved HERBERT GIRON
ELECTRICAL-Final 10/28/2022 Corrections Issued HERBERT GIRON
Final 10/28/2022 Corrections Issued HERBERT GIRON
Gas Test 10/28/2022 Approved HERBERT GIRON
Green Building Final 10/28/2022 Approved HERBERT GIRON
Green Building Rough 10/28/2022 Approved HERBERT GIRON
HVAC-Final 10/28/2022 Corrections Issued HERBERT GIRON
PLUMBING-Final 10/28/2022 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 10/28/2022 SGSOV Approved HERBERT GIRON
Service/Power Release 10/28/2022 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 10/28/2022 Approved HERBERT GIRON
ELECTRICAL-Final 11/4/2022 Approved HERBERT GIRON
Final 11/4/2022 OK to Issue CofO HERBERT GIRON
HVAC-Final 11/4/2022 Approved HERBERT GIRON
Service/Power Release 11/4/2022 Approved HERBERT GIRON