7419 N DARBY AVE 91335
Certificate Information: 7419 N DARBY AVE 91335
- Application / Permit
- 21014-20000-04639
- Plan Check / Job No.
- B21VN12428
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' DETACHED GARAGE AND ADD 13' X 20' FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(B). ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/8/2021
- Issuing Office
- Current Status
- CofO Issued on 8/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2021 | JENNIFER LEE |
| Corrections Issued | 9/15/2021 | JENNIFER LEE |
| Plan Check Approved | 11/30/2021 | JENNIFER LEE |
| Issued | 12/8/2021 | APPLICANT |
| Building Plans Picked Up | 12/17/2021 | APPLICANT |
| CofO in Progress | 7/12/2022 | JEFFREY BULL |
| CofO Issued | 8/12/2022 | JOHN JANSON |
| Permit Finaled | 8/12/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/4/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 11/4/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/23/2021 | ROSE MARIE SMITH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/16/2022 | Partial Approval | VINCENT HANLEY |
| Sewer | 2/16/2022 | Approved | VINCENT HANLEY |
| Underground Mechanical | 2/16/2022 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 2/23/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/23/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/16/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 3/16/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/30/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 3/30/2022 | Approved | VINCENT HANLEY |
| Insulation | 3/30/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/30/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/5/2022 | Approved | JUSTIN HAWLEY |
| Final | 5/26/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 5/26/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/26/2022 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 5/26/2022 | Approved | VINCENT HANLEY |
| Final | 6/30/2022 | Not Ready for Inspection | JEFFREY BULL |
| Final | 7/11/2022 | OK to Issue CofO | JEFFREY BULL |