19811 W SEPTO ST 91311
Certificate Information: 19811 W SEPTO ST 91311
- Application / Permit
- 21014-20000-04626
- Plan Check / Job No.
- B21VN12384
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (9'-8"x8'-6") 79 SQFT ADDITION AND (21'-4"x6'-7") NEW PATIO COVER AND INTERIOR REMODEL TO THE (E) SFD. SEE COMMENTS.
- Permit Issued
- Issued on 10/6/2021
- Issuing Office
- Current Status
- CofO Issued on 11/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2021 | PETER MOSESIAN |
| Corrections Issued | 9/15/2021 | PETER MOSESIAN |
| Applicant returned to address corrections | 9/29/2021 | PETER MOSESIAN |
| Plan Check Approved | 10/6/2021 | PETER MOSESIAN |
| Issued | 10/6/2021 | APPLICANT |
| CofO in Progress | 4/27/2022 | ARIS ALLAHVERDIAN |
| CofO in Progress | 4/27/2022 | ARIS ALLAHVERDIAN |
| CofO Issued | 11/6/2024 | DAVID JAMES |
| Permit Finaled | 11/6/2024 | DAVID JAMES |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/17/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tosounian,, Oshin Bedros; Lic. No.: S3730 | 7136 HASKELL AVE STE 301 VAN NUYS, CA 91406 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/13/2021 | Approved | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 10/28/2021 | Approved | HAGOP BADOSSIAN |
| ELECTRICAL-Rough | 10/28/2021 | Approved | HAGOP BADOSSIAN |
| Green Building Rough | 10/28/2021 | Approved | HAGOP BADOSSIAN |
| HVAC-Rough | 10/28/2021 | Approved | HAGOP BADOSSIAN |
| PLUMBING-Rough | 10/28/2021 | Approved | HAGOP BADOSSIAN |
| Drywall Nailing | 4/26/2022 | Approved | ARIS ALLAHVERDIAN |
| Final | 4/26/2022 | OK to Issue CofO | ARIS ALLAHVERDIAN |
| Footing/Foundation/Slab | 4/26/2022 | Approved | ARIS ALLAHVERDIAN |
| Green Building Final | 4/26/2022 | Approved | ARIS ALLAHVERDIAN |
| SGSOV-Seismic Gas S/O Valve | 4/26/2022 | SGSOV Approved | ARIS ALLAHVERDIAN |
| Smoke Detectors | 4/26/2022 | Approved | ARIS ALLAHVERDIAN |