3657 W GLENEAGLES DR 91356

Certificate Information: 3657 W GLENEAGLES DR 91356

Application / Permit
21014-20000-04624
Plan Check / Job No.
B21VN12383
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW FRONT PORCH ADDITION (18'-4" X 12'-3") W/ HIGH CEILING/ROOF. REMOVE AND REPLACE EX BALCONY GUARDRAILS PER PLAN.
Permit Issued
Issued on 12/1/2022
Issuing Office
Valley
Current Status
CofO in Progress on 1/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/15/2021 APPLICANT
Assigned to Plan Check Engineer 9/17/2021 JEROME MAGAT PALMA
Corrections Issued 9/20/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 11/10/2022 ANTOAN MISHRIKI
Applicant returned to address corrections 11/21/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 11/23/2022 MIROOSH KHACHATOORIAN
Plan Check Approved 12/1/2022 ISIS ARGUETA
Issued 12/1/2022 APPLICANT
CofO in Progress 5/22/2024 JOHN KIDWELL
No Progress 1/15/2025 SEAN WIRCH
CofO in Progress 1/15/2025 SEAN WIRCH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/29/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/30/2021 CARLOS AGUILERA
ZA Case Cleared 12/20/2021 PABLO ESTRADA
Grading Pre-Inspection Cleared 11/22/2022 VASIL MIHALEV
Specific Plan Cleared 11/29/2022 OLGA AYALA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/30/2023 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 2/15/2023 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 2/21/2023 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Approved DAVID SANDOVAL
ELECTRICAL-Rough 3/30/2023 Approved DAVID SANDOVAL
Interior/Exterior Lathing 4/5/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 2/14/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 2/14/2024 Partial Approval JOHN KIDWELL
Final 4/15/2024 Corrections Issued JOHN KIDWELL
Smoke Detectors 4/15/2024 Approved JOHN KIDWELL
Final 4/25/2024 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Final 5/21/2024 Approved JOHN KIDWELL
Final 5/21/2024 OK to Issue CofO JOHN KIDWELL
HVAC-Final 5/21/2024 Approved JOHN KIDWELL
PLUMBING-Final 5/21/2024 Approved JOHN KIDWELL