3978 S MCLAUGHLIN AVE 90066
Certificate Information: 3978 S MCLAUGHLIN AVE 90066
- Application / Permit
- 21014-20000-04564
- Plan Check / Job No.
- B21VN12202
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED (18'-3"x20'-3"),368 SQFT GARAGE TO ADU WITH (15'-0"x10'-0"),278 SQFT PER LAMC 12.22 A.33 (c)(d) W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 6/6/2022
- Issuing Office
- Current Status
- CofO Issued on 8/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | PETER MOSESIAN |
| Corrections Issued | 10/13/2021 | PETER MOSESIAN |
| Quality Review Completed | 10/20/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 10/27/2021 | APPLICANT |
| Applicant returned to address corrections | 4/21/2022 | PETER MOSESIAN |
| Plan Check Approved | 5/24/2022 | PETER MOSESIAN |
| Issued | 6/6/2022 | APPLICANT |
| CofO in Progress | 8/27/2023 | RICHARD STEINBACH |
| Permit Finaled | 8/29/2023 | DANIEL ORRANTE |
| CofO Issued | 8/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/2/2021 | WESTON PRINGLE |
| Address approval | Cleared | 12/15/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 12/15/2021 | HISASHI KOBAYAKAWA |
| Construction near power lines | Cleared | 3/22/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/16/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/18/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/15/2022 | Corrections Issued | PATRICK QUALEY |
| Excavation/Setback/Form/Re-Bar | 6/24/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/24/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 6/24/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 9/21/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/21/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/21/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 10/21/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 10/21/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/21/2022 | Approved | JESUS RODRIGUEZ |
| Sewer | 10/21/2022 | Partial Approval | JESUS RODRIGUEZ |
| Underground Mechanical | 10/21/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 11/29/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 11/29/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 11/29/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/29/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 12/9/2022 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 1/31/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 1/31/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 8/18/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/18/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 8/18/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 8/23/2023 | Approved | JESUS RODRIGUEZ |
| Final | 8/23/2023 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Final | 8/23/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 8/23/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/23/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 8/23/2023 | Approved | JESUS RODRIGUEZ |