19123 W ROSITA ST 91356

Certificate Information: 19123 W ROSITA ST 91356

Application / Permit
21014-20000-04554
Plan Check / Job No.
B21VN12184
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF AN IRREGULAR 14.5' x 21' (246 SQ. FT.) TO THE SECOND STORY OF THE (E) SINGLE-FAMILY DWELLING.
Permit Issued
Issued on 11/18/2021
Issuing Office
Current Status
Issued on 11/18/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/9/2021 APPLICANT
Assigned to Plan Check Engineer 9/10/2021 LUIS RINCON
Corrections Issued 9/11/2021 LUIS RINCON
Applicant returned to address corrections 10/15/2021 LUIS RINCON
Applicant returned to address corrections 11/16/2021 LUIS RINCON
Plan Check Approved 11/18/2021 LUIS RINCON
Issued 11/18/2021 APPLICANT
Building Plans Picked Up 11/22/2021 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 9/30/2021 STEVEN WECHSLER
Miscellaneous Cleared 9/30/2021 STEVEN WECHSLER
Roof/Waste drainage to street Cleared 10/1/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/5/2021 CARLOS AGUILERA

Contact Information

Contractor Boutique Construction; Lic. No.: 1051070-B 21208 COSTANSO STREET #1      WOODLAND HILLS, CA 91364
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Not Ready for Inspection SEAN HAUPT
Footing/Foundation/Slab 1/7/2022 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 1/18/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 1/18/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 1/18/2022 Corrections Issued DAVID SANDOVAL
Green Building Rough 1/18/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 1/18/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 1/27/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 1/27/2022 Approved DAVID SANDOVAL
Insulation 1/27/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 1/27/2022 Partial Approval DAVID SANDOVAL
Shower Pan 1/27/2022 Corrections Issued DAVID SANDOVAL
Interior/Exterior Lathing 1/31/2022 Corrections Issued DAVID SANDOVAL
Shower Pan 1/31/2022 Corrections Issued DAVID SANDOVAL
Deputy Wood Construction 2/1/2022 Conditional Approval DAVID SANDOVAL
Interior/Exterior Lathing 2/2/2022 Approved DAVID SANDOVAL
Shower Pan 2/2/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 2/3/2022 Approved DAVID SANDOVAL
Drywall Nailing 2/3/2022 Approved DAVID SANDOVAL
Green Building Rough 2/3/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 3/24/2022 Approved DAVID SANDOVAL
Final 4/18/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 4/18/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 4/18/2022 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 4/18/2022 Approved DAVID SANDOVAL
Final 5/20/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 5/20/2022 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 5/20/2022 SGSOV Approved DAVID SANDOVAL