2554 N HUTTON DR 90210
Certificate Information: 2554 N HUTTON DR 90210
- Application / Permit
- 21014-20000-04549
- Plan Check / Job No.
- B21VN12174
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 247 SQ. FT. ADDITION TO THE (E) BEDROOM, AND CONVERT A 45 SQ. FT. PORTION OF THE (E) GARAGE INTO THE (E) SFD.
- Permit Issued
- Issued on 11/15/2021
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | JESSE ARELLANO |
| Corrections Issued | 9/9/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 10/29/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 11/9/2021 | JESSE ARELLANO |
| Issued | 11/15/2021 | APPLICANT |
| Building Plans Picked Up | 11/16/2021 | APPLICANT |
| CofO in Progress | 12/15/2022 | GERMAN RODRIGUEZ MENDOZA |
| Permit Finaled | 12/17/2022 | DANIEL ORRANTE |
| CofO Issued | 12/17/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/17/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 9/30/2021 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2021 | TRACY TATE |
| Roof/Waste drainage to street | Cleared | 9/30/2021 | TRACY TATE |
| Sewer availability | Cleared | 9/30/2021 | TRACY TATE |
| Grading Pre-Inspection | Cleared | 10/4/2021 | BRIAN MILLER |
| Green Code | Cleared | 10/29/2021 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/22/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 2/24/2022 | Approved | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 3/18/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 4/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| MERV13>=Rough | 4/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 4/11/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 7/6/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| MERV13>=Rough | 7/6/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 7/6/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 7/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 7/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 7/11/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 7/11/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| MERV13>=Rough | 7/11/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/11/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 7/11/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 7/12/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 7/12/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 7/12/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/12/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Wood Construction | 7/14/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 7/14/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 12/13/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 12/13/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| MERV13>=Final | 12/13/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 12/13/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |