9000 N SYLMAR AVE 91402
Certificate Information: 9000 N SYLMAR AVE 91402
- Application / Permit
- 21014-20000-04541
- Plan Check / Job No.
- B21VN12127
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition of an 11'-11" x 10'-3" patio cover per engineer design to join the (E) ALQ to the (E) SFD. Convert the ALQ into a recreation room and storage.
- Permit Issued
- Issued on 10/12/2021
- Issuing Office
- Current Status
- CofO Issued on 7/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2021 | ANGELICA DAVE |
| Corrections Issued | 9/21/2021 | OMAR GARNICA |
| Applicant returned to address corrections | 10/5/2021 | OMAR GARNICA |
| Plan Check Approved | 10/12/2021 | OMAR GARNICA |
| Issued | 10/12/2021 | APPLICANT |
| Building Plans Picked Up | 10/12/2021 | APPLICANT |
| CofO in Progress | 7/13/2022 | GREGG CUMMINGS |
| CofO Issued | 7/14/2022 | MICHAEL SMITH |
| Permit Finaled | 7/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | D H Property Maintenance Inc; Lic. No.: 985811-B | 11312 COVELLO STREET SUN VALLEY, CA 91352 |
| Engineer | Shagirian,, Ashot; Lic. No.: C79415 | 11337 RUNNYMEDE ST SUN VALLEY, CA 91352 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 12/7/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 12/10/2021 | Approved | MATTHEW NELSON |
| Final | 12/23/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/23/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 12/23/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 1/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 1/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Special/Order Compliance | 2/1/2022 | Approved | GREGG CUMMINGS |
| Final | 3/16/2022 | Corrections Issued | GREGG CUMMINGS |
| Final | 3/16/2022 | Partial Inspection | KRISTEN CAUSEY |
| Smoke Detectors | 3/16/2022 | Approved | GREGG CUMMINGS |
| Final | 7/5/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/5/2022 | Approved | GREGG CUMMINGS |
| Final | 7/11/2022 | Corrections Issued | GREGG CUMMINGS |
| Final | 7/13/2022 | OK to Issue CofO | GREGG CUMMINGS |